Any bopdy tell me how to prepare rate analysis for
Centering and shuttering for RAFT FOUNDATION, SUSPENDED
FLOORS, STAIR CASES, RETAINING WALLS, SHEAR WALL and COLUMNS
Answer / praman kumar srivastava
Providing, erecting, fixing in position striking/ removing
and cleaning shuttering and centering for formwork in
foundation and Plinth at all locations for all shapes
inclufing chamfers, camber, splays, keys, wedges, props,
rail, bracing , brackets, cutti
Foundation. For 10.8 Sqmt Area (Based on Physical Analysis)
Material :
Ply Wood Sqmt 11.000 538.000 5918.000
Nut Bolts, Balli Battens etc LS
1095.000
For 15 Repetation 7013.000
For 1 467.533
Labour :
Carpenter I Class Nos 0.750 175.000 131.250
Beldar skilled Nos 1.500 135.000 202.500
Shuttering Oil LS 1.000 33.400 33.400
Sundries I Time 16.700 1.690 28.223
862.906
Add for water charges @ 1%
8.629
Total 871.535
Add for contractor's profit and overheads @ 10%
148.161
Cost for 10.8 sqm 1019.696
Cost of 01 Sqmt 94.416
Say 94
| Is This Answer Correct ? | 7 Yes | 2 No |
how amny bricks of size 240 mm X 120 mm X70 mm are required in 100 cubic meter brickwork. How much cement is required at 10 mm masonry and at 4:1 sand cement ratio and how much cubic meter of sand is required for the above work.
what is superbuilt-up area in flats & how it is calculate?
how to calculate quantity of cement and sand for plastering works in CM 1:6 proportion.....plz answer anyone.....and write the formula...
What is capicity of cap lock scffolding stander(vertical member) and ledger of different size?
Which architectural movement is also known as jazz moderna?
what is workability,define it?
how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches
what does a civil engineer should know?
how much steel and concrete required for 450 sft slab? tell also the method
load combinations how many types for staad design purpose?
How to calculate Rate of 10 cum of Brick masonary,if the rate of material are as fallow? sand=Rs.500/mt Brick=Rs.5/brick Labour=Rs 300/day Free issue=cement+water+electicity.
What is Time at Large?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)