Answer / pranav
Calculate the quantity of coarse aggregate + sand +cement +
method of placement + shuttering + method of curing
| Is This Answer Correct ? | 83 Yes | 12 No |
Answer / g pavan kumar
calculate the coarse aggreate+cement+quality
expensis+considered traveling charges+electric power
charge+technical persons charge+shurtring+curing cost and
additional mixing cost.
| Is This Answer Correct ? | 11 Yes | 1 No |
Answer / simarpreet upweja
Total Cost will be Material cost + Labour cost + Mode of pouring + mode of mixing and transit + Shuttering Cost + Curing cost in later stage
Material cost will include cost of water + Recron(any fiber if adding) + admixer + coarse aggegate + fine aggregate + sand + Cement + Flyash (if using crush sand).
There are many ways of mixing.
i) If using batching plant then cost of transit millers and plant.
ii) If mixing is done at site by mixer then there will be no cost of transit.
iii) If mixing is done manually then it will be covered under labour cost.
Labour Cost : Self Explanatory
Shuttering Cost : As per surface area multiplied by cost per unit area.
Curing Cost : Self explanatory. Curing can be done by many ways so first you will have to decide method.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / fayyaz tabussam
calculate the concrete batching plant running cost,material
cost,shuttering cost,curing cost.
| Is This Answer Correct ? | 15 Yes | 17 No |
Which is the latest version of solidsworks?
how to calculate the no of cement bags required for 100sqft of area 12 mm thick plastering in proportion of 1:3,1:4,1:5,1:6?
why & what is perchatage we are using fly ash in concrete?
wha is frog?
Any body tell me how can we calculate 1m3 quantity of cement sand aggregrate in kg.
how we can calculate the quantity of sand & cement & also Aggregate so give me to this answer for a slab Length is : 25' /3.28 = 7.62 Mtr Width is : 30' /3.28 = 9.14 Mtr Depth is : 0.6"/3.28 = 0.15 2Mtr
what are the strenth of 1cum brick work
how is calculate the developement length of column such like as L
what is the formula for calculating volume of isolated footing? i am not asking for the sloped footing, i am asking for normal rectangle isolated footing, pls add diagram or linkof diagram with answere
can anybody provide me the HPCL apptitude papers?am having the test on march 2008 so plz
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
Water absorption for stone and first class stone bricks?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)