tell me quantitys of matal, sand and cement in 1:4:8 and
1:2:4
Answers were Sorted based on User's Feedback
Answer / tejaswi
for 1 unit of cement , 4 units of sand and 8 units of
matal are added in 1:4:8 mix.
And for 1 unit of cement, 2 units of sand and 4 units of
matal are added in 1:2:4 mix.
Is This Answer Correct ? | 166 Yes | 39 No |
Answer / ramesh
Generally 1:4:8 concrete mix used for plain cement concrete
For making 1cum pcc required
40mm metal :0.92 cum
sand :0.46
cement :0.115 cum or 3.312 bags
Is This Answer Correct ? | 127 Yes | 20 No |
If you are considering 1:4:8; per each cubic meter you have
to arrive the quantities as under.
If 1+4+8= 1cum (dry mix); then
cement quantity will be 1/13 = 0.077 cum;(2.2 Bags of 50kg)
Sand Quantity will be 4/13= 0.31 cum and
the Quantity of Coarse aggregate shall be 8/13=0.62 cum.
But, the volume of dry concrete will be 1.5 times
(approx)the volume of wet concrete. So, if you want to
prepare a cum of wet concrete, multiply the above values by 1.5.
Is This Answer Correct ? | 90 Yes | 21 No |
Answer / mask
* In 1:4:8
Cement - 1.25 Cft
Sand - 5 Cft
Matal - 10 Cft
*In 1:2:4
Cement - 1.25 Cft
Sand - 2.5 Cft
Matal - 5 Cft
Is This Answer Correct ? | 45 Yes | 10 No |
Answer / navneet
the mix contains 1 part of cement, 2 parts of fine aggregate
and 4 parts of coarse aggregate
Is This Answer Correct ? | 23 Yes | 7 No |
Answer / narendra pawar
Generally 1:4:8 concrete mix used for plain cement concrete
For making 1cum pcc required
metal :0.616 cum
sand :0.308
cement :0.077 cum
0.077 + 0.308 + 0.616 = 1.001 cum
Is This Answer Correct ? | 26 Yes | 12 No |
Answer / vishal kumar chy
1:2:4 It means 1 unit of cement, 2 units of sand , 4 units of aggregates
Is This Answer Correct ? | 13 Yes | 2 No |
Answer / kailash
1:2:4 & 1:4:8 its not a standard design. design depends
upon the which aggregate available at site and there
density.
Is This Answer Correct ? | 10 Yes | 10 No |
Answer / suraj
in 1:2:4 mixture 1 part is cement 2 part is coarse sand and
4 part is fine sand matal is nothing
Is This Answer Correct ? | 16 Yes | 27 No |
What will be compressive strength of concrete casted in PPC in the 7 days period with M20 grade.
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
among fine,coarse sand which is used for plaster, brickwork and RCC & why?
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
Special thing in designing a overhead reservoir ? which is different from an ordinary design
what u mean by M20
9 Answers Srinidhi Constructions,
What is difference between combin footing & rapt footing
Please explain soil invistigation methods?
what is project planning
How to design staircase.plz tell me formula for the design the staircase.
step by step procedure to find out the percentage of steel in coloum,beam,slab,footing in detailed
Weather we heat cement, will it changes its color? if yes why? if no why?