tell me quantitys of matal, sand and cement in 1:4:8 and
1:2:4
Answers were Sorted based on User's Feedback
Answer / tejaswi
for 1 unit of cement , 4 units of sand and 8 units of
matal are added in 1:4:8 mix.
And for 1 unit of cement, 2 units of sand and 4 units of
matal are added in 1:2:4 mix.
Is This Answer Correct ? | 166 Yes | 39 No |
Answer / ramesh
Generally 1:4:8 concrete mix used for plain cement concrete
For making 1cum pcc required
40mm metal :0.92 cum
sand :0.46
cement :0.115 cum or 3.312 bags
Is This Answer Correct ? | 127 Yes | 20 No |
If you are considering 1:4:8; per each cubic meter you have
to arrive the quantities as under.
If 1+4+8= 1cum (dry mix); then
cement quantity will be 1/13 = 0.077 cum;(2.2 Bags of 50kg)
Sand Quantity will be 4/13= 0.31 cum and
the Quantity of Coarse aggregate shall be 8/13=0.62 cum.
But, the volume of dry concrete will be 1.5 times
(approx)the volume of wet concrete. So, if you want to
prepare a cum of wet concrete, multiply the above values by 1.5.
Is This Answer Correct ? | 90 Yes | 21 No |
Answer / mask
* In 1:4:8
Cement - 1.25 Cft
Sand - 5 Cft
Matal - 10 Cft
*In 1:2:4
Cement - 1.25 Cft
Sand - 2.5 Cft
Matal - 5 Cft
Is This Answer Correct ? | 45 Yes | 10 No |
Answer / navneet
the mix contains 1 part of cement, 2 parts of fine aggregate
and 4 parts of coarse aggregate
Is This Answer Correct ? | 23 Yes | 7 No |
Answer / narendra pawar
Generally 1:4:8 concrete mix used for plain cement concrete
For making 1cum pcc required
metal :0.616 cum
sand :0.308
cement :0.077 cum
0.077 + 0.308 + 0.616 = 1.001 cum
Is This Answer Correct ? | 26 Yes | 12 No |
Answer / vishal kumar chy
1:2:4 It means 1 unit of cement, 2 units of sand , 4 units of aggregates
Is This Answer Correct ? | 13 Yes | 2 No |
Answer / kailash
1:2:4 & 1:4:8 its not a standard design. design depends
upon the which aggregate available at site and there
density.
Is This Answer Correct ? | 10 Yes | 10 No |
Answer / suraj
in 1:2:4 mixture 1 part is cement 2 part is coarse sand and
4 part is fine sand matal is nothing
Is This Answer Correct ? | 16 Yes | 27 No |
what is anchorage? Why anchoring of reinforcing bars necessary and what are the shapes ?
for assembly supported beam main bar are provided at ?
How many types of stirrups are there? How to calculate their cut lengths?
What is the role of a PMC(project management consultancy) in any construction work?
How many jacks and props required for one floor, or tell me any thumbrule...to know the approx jacks and props required.?
What is a tensile strength? What is the tensile strength of wood?
What is the correct position of lapping splice of reinforcement steel bars in a beam at top & bottom of the beam?? what is the reason for this location?..what are the factors affecting lapping location in beam?
Explain what are the phases inspections are done by local authority while construction?
Minimum spacing of 2- bars in column, beam, slab
Why curing is necessary for concrete
how much overlap i must to provide in column 16mm dia bar and if i want to save steel by doing welding then how much over lap must be?
3 Answers Bin Hamda Trading Contracting,
mix design of concrete using indian standard methods