tell me quantitys of matal, sand and cement in 1:4:8 and 1:2:4..

Answer / tejaswi

for 1 unit of cement , 4 units of sand and 8 units of
matal are added in 1:4:8 mix.

And for 1 unit of cement, 2 units of sand and 4 units of
matal are added in 1:2:4 mix.

Is This Answer Correct ?    166 Yes 39 No

tell me quantitys of matal, sand and cement in 1:4:8 and 1:2:4..

Answer / ramesh

Generally 1:4:8 concrete mix used for plain cement concrete

For making 1cum pcc required

40mm metal :0.92 cum

sand :0.46

cement :0.115 cum or 3.312 bags

Is This Answer Correct ?    127 Yes 20 No

tell me quantitys of matal, sand and cement in 1:4:8 and 1:2:4..

Answer / surya v kuchibhotla

If you are considering 1:4:8; per each cubic meter you have
to arrive the quantities as under.
If 1+4+8= 1cum (dry mix); then
cement quantity will be 1/13 = 0.077 cum;(2.2 Bags of 50kg)
Sand Quantity will be 4/13= 0.31 cum and
the Quantity of Coarse aggregate shall be 8/13=0.62 cum.

But, the volume of dry concrete will be 1.5 times
(approx)the volume of wet concrete. So, if you want to
prepare a cum of wet concrete, multiply the above values by 1.5.

Is This Answer Correct ?    90 Yes 21 No

tell me quantitys of matal, sand and cement in 1:4:8 and 1:2:4..

Answer / mask

* In 1:4:8
Cement - 1.25 Cft
Sand - 5 Cft
Matal - 10 Cft
*In 1:2:4
Cement - 1.25 Cft
Sand - 2.5 Cft
Matal - 5 Cft

Is This Answer Correct ?    45 Yes 10 No

tell me quantitys of matal, sand and cement in 1:4:8 and 1:2:4..

Answer / navneet

the mix contains 1 part of cement, 2 parts of fine aggregate
and 4 parts of coarse aggregate

Is This Answer Correct ?    23 Yes 7 No

tell me quantitys of matal, sand and cement in 1:4:8 and 1:2:4..

Answer / narendra pawar

Generally 1:4:8 concrete mix used for plain cement concrete

For making 1cum pcc required

metal :0.616 cum

sand :0.308

cement :0.077 cum

0.077 + 0.308 + 0.616 = 1.001 cum

Is This Answer Correct ?    26 Yes 12 No

tell me quantitys of matal, sand and cement in 1:4:8 and 1:2:4..

Answer / vishal kumar chy

1:2:4 It means 1 unit of cement, 2 units of sand , 4 units of aggregates

Is This Answer Correct ?    13 Yes 2 No

tell me quantitys of matal, sand and cement in 1:4:8 and 1:2:4..

Answer / kailash

1:2:4 & 1:4:8 its not a standard design. design depends
upon the which aggregate available at site and there
density.

Is This Answer Correct ?    10 Yes 10 No

tell me quantitys of matal, sand and cement in 1:4:8 and 1:2:4..

Answer / suraj

in 1:2:4 mixture 1 part is cement 2 part is coarse sand and
4 part is fine sand matal is nothing

Is This Answer Correct ?    16 Yes 27 No

Post New Answer

More Civil Engineering Interview Questions

what is anchorage? Why anchoring of reinforcing bars necessary and what are the shapes ?

6 Answers  


for assembly supported beam main bar are provided at ?

2 Answers   TCS,


How many types of stirrups are there? How to calculate their cut lengths?

2 Answers   BARC,


What is the role of a PMC(project management consultancy) in any construction work?

2 Answers  


How many jacks and props required for one floor, or tell me any thumbrule...to know the approx jacks and props required.?

1 Answers   Sumadhura Infracon,






What is a tensile strength? What is the tensile strength of wood?

0 Answers  


What is the correct position of lapping splice of reinforcement steel bars in a beam at top & bottom of the beam?? what is the reason for this location?..what are the factors affecting lapping location in beam?

6 Answers   SPCL,


Explain what are the phases inspections are done by local authority while construction?

0 Answers  


Minimum spacing of 2- bars in column, beam, slab

10 Answers  


Why curing is necessary for concrete

6 Answers  


how much overlap i must to provide in column 16mm dia bar and if i want to save steel by doing welding then how much over lap must be?

3 Answers   Bin Hamda Trading Contracting,


mix design of concrete using indian standard methods

10 Answers   CCCL,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)