tell me quantitys of matal, sand and cement in 1:4:8 and
1:2:4
Answers were Sorted based on User's Feedback
Answer / tejaswi
for 1 unit of cement , 4 units of sand and 8 units of
matal are added in 1:4:8 mix.
And for 1 unit of cement, 2 units of sand and 4 units of
matal are added in 1:2:4 mix.
| Is This Answer Correct ? | 166 Yes | 39 No |
Answer / ramesh
Generally 1:4:8 concrete mix used for plain cement concrete
For making 1cum pcc required
40mm metal :0.92 cum
sand :0.46
cement :0.115 cum or 3.312 bags
| Is This Answer Correct ? | 127 Yes | 20 No |
If you are considering 1:4:8; per each cubic meter you have
to arrive the quantities as under.
If 1+4+8= 1cum (dry mix); then
cement quantity will be 1/13 = 0.077 cum;(2.2 Bags of 50kg)
Sand Quantity will be 4/13= 0.31 cum and
the Quantity of Coarse aggregate shall be 8/13=0.62 cum.
But, the volume of dry concrete will be 1.5 times
(approx)the volume of wet concrete. So, if you want to
prepare a cum of wet concrete, multiply the above values by 1.5.
| Is This Answer Correct ? | 90 Yes | 21 No |
Answer / mask
* In 1:4:8
Cement - 1.25 Cft
Sand - 5 Cft
Matal - 10 Cft
*In 1:2:4
Cement - 1.25 Cft
Sand - 2.5 Cft
Matal - 5 Cft
| Is This Answer Correct ? | 45 Yes | 10 No |
Answer / navneet
the mix contains 1 part of cement, 2 parts of fine aggregate
and 4 parts of coarse aggregate
| Is This Answer Correct ? | 23 Yes | 7 No |
Answer / narendra pawar
Generally 1:4:8 concrete mix used for plain cement concrete
For making 1cum pcc required
metal :0.616 cum
sand :0.308
cement :0.077 cum
0.077 + 0.308 + 0.616 = 1.001 cum
| Is This Answer Correct ? | 26 Yes | 12 No |
Answer / vishal kumar chy
1:2:4 It means 1 unit of cement, 2 units of sand , 4 units of aggregates
| Is This Answer Correct ? | 13 Yes | 2 No |
Answer / kailash
1:2:4 & 1:4:8 its not a standard design. design depends
upon the which aggregate available at site and there
density.
| Is This Answer Correct ? | 10 Yes | 10 No |
Answer / suraj
in 1:2:4 mixture 1 part is cement 2 part is coarse sand and
4 part is fine sand matal is nothing
| Is This Answer Correct ? | 16 Yes | 27 No |
CROSS SLOPE OF Macadam Construction
if any chance to getting a set of solved major building estimate with the drawing.(soft copy)
what is the code for classification of bricks
what is the use of dowels rod..?
resins are not soluble in water soluble in spirit used in varnish left behind on evoporation of oil
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
what are the Cement Coefficient for Block Work & plastering Work?
How many type thickness vibrator used in concreting,,?
reinforcement lapping for short pile and long pile
how to shuttering is used in slab
How to calculate steel quantity in beam and column?
How do you calculate the surface area of the paver blocks, in oreder to find out the compressive strength of the same ?? And which codes are used for testing of paver blocks ?
1 Answers BP Sangle Constructions, ECMAS,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)