WHAT IS THE RATIO OF CEMENT:SAND:COARSE AGGREGADE IN M-20,
M-25, M-30, M-35, M-40, M-45, M-50 CONCRETE?

Answers were Sorted based on User's Feedback



WHAT IS THE RATIO OF CEMENT:SAND:COARSE AGGREGADE IN M-20, M-25, M-30, M-35, M-40, M-45, M-50 CONC..

Answer / vignesh selvaji

M10- 1:3:6, M15- 1:2:4, M20-1:1.5:3, M25-1:1:2 Remaining grades from M30 to M50 which is varied based on the design mix.

Is This Answer Correct ?    5 Yes 3 No

WHAT IS THE RATIO OF CEMENT:SAND:COARSE AGGREGADE IN M-20, M-25, M-30, M-35, M-40, M-45, M-50 CONC..

Answer / sarvamangala

Please note that the mix design and water cement ratio
depending upon various factors, such as type of cement,
aggregate, site conditions, etc.
The mix design provided here is for reference purpose only.
Actual site conditions vary and thus this should be adjusted
as per the location and other factors
Ratio's are like this,
Cement:Fine aggregate(Kg/m3):Coarse aggregate(kg/m3):Water
(l/m3):Plasticizer (l/m3)

1) M60: 1:1.35:2.19:0.29:0.8

2) M50: 1:1.472:3.043:0.35:0.012

3) M40: 1:1.65:2.92:0.4:0.006

4) M35: 1:1.76:3.18:0.4:0.005

5) M30: 1:1.87:3.38:0.42:0.005

6) M20: 1:2.4:4.93:0.5:nil

Thank you

Is This Answer Correct ?    5 Yes 18 No

Post New Answer

More Civil Engineering Interview Questions

How many modular bricks are required for 1 cubic meter of brick masonry?

14 Answers   ITI, L&T,


I am a civil engineering student and going to attend interview in this week in an IT company.Will they ask me questions about my area of interest or cs

0 Answers   Satyam,


appsc AEE'S interview questions wanted

3 Answers   APPSC,


What are advancements in civil engineering?

0 Answers  


why we are placing the beam under the plinth wall?

4 Answers  






Please tell me about building work from begining

2 Answers  


RCC colums of 15"X9" each, roof height 10.5'ft, total pillars 12 nons. Span between pillar to pillar is 14/20/20 length wise and 17/14 width wise. Total Slab area 2400 sft and plinth area is 1900 sft. beams are 12"X12". kindly calculate load factor per sqft.

2 Answers   ABS Construction, L&T,


beam is fixed at both end which is 8 m span carry udl of 10 kn/m at left half span.there is internal hinge at center.what is reaction at center

1 Answers   IES,


what is pile and deam foundation

0 Answers   DLF,


What are the uses of layer?

0 Answers  


Where do we use singly and doubly reinforced beam in construction purposes

2 Answers   Isha Homes, Simplex, Sterling Wilson,


what grade of concrete to be used for lintel when reinforced with bamboo in place of steel?????????

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)