tell me quantitys of matal, sand and cement in 1:4:8 and
1:2:4
Answer Posted / narendra pawar
Generally 1:4:8 concrete mix used for plain cement concrete
For making 1cum pcc required
metal :0.616 cum
sand :0.308
cement :0.077 cum
0.077 + 0.308 + 0.616 = 1.001 cum
| Is This Answer Correct ? | 26 Yes | 12 No |
Post New Answer View All Answers
residential buildings,mixing of concrete,structural,construction material,site handling.
What distance in meters on the ground is the equivalent of one second of arc in longitude or latitude?
How many days should curing of plastering, brick work and concrete
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
What is the cost difference between site mix and ready mix concrete per cubic meter
Howmuch bend to be provide for 200/600 BEEM
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
What in your past experience or education prepares you for the position for which you are applying
how we can find sieve #4 is 4.75mm?
How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel
what is differences between ferrock and concrete ?
What is the unit standard weight,thicknessof C.I>Pipe of various Dia upto200 MM(as per IS1538)
what is the weight of 6000 psi concrete in lb/cft?
Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,