Answer / pradeep kumar
M25, actually it is design mix so we cannot say exact ratio for this grade but approximately the ratio is 1:1:2,
for preparing 1m3 of concrete, 1.5 m3 need to be taken.
Hence, 1:1:2 - 1+1+2=4,
Volume of the cement= 1/4*1.5 = 0.375
Unit weight of cement = 1440 kg/m3
so weight of cement = 0.375*1440 = 540 Kgs.
Hence, 1 m3 of M25 grade concrete is required 540 kgs of cement
| Is This Answer Correct ? | 7 Yes | 8 No |
Answer / ms
M25=1:1:2
50kg cement=1.25 cft
1.25cft=5cft concrete of M25
So. =1.25÷5
=.25 cement is the 1cft concrete
=.25×35.28
=8.82cft cement/M3
=8.82×41
=361.62÷50
=7.23 bags is required ok
| Is This Answer Correct ? | 2 Yes | 4 No |
Answer / muhammad rizwan hashmi (pakist
M25 Ratio of concrete = 1:1:2
Sum of ratio =4
Quantity of Cement (dry material) = 1/4*1.54
= 0.385 cu.m
1 bag = 0.0354 cu.m
= 0.385/0.0354
= 10.88 bags
1 bag = 50 kgs
Cemeent: 10.88 *50 =543kgs
| Is This Answer Correct ? | 14 Yes | 27 No |
Answer / raman
M25:-1:2:4 mix
and 6.5 bags about
means 325 kgs
| Is This Answer Correct ? | 14 Yes | 42 No |
Answer / bala
* M25 - 1:1:2
Cement Reqd is - 610Kgs per cu.m(12.2Bags)
| Is This Answer Correct ? | 8 Yes | 51 No |
Answer / vijay
M25 -1:1:2
volume of coarse aggregate in 1cum=0.95cum
vol. of sand =0.95/2=.475
hence vol. of cement=vol. of sand
vol. of 1 bag of cement =0.035cum
no. of bag required=.475/.035=14 bags
cement=50*14=700kg
| Is This Answer Correct ? | 5 Yes | 48 No |
What is the concepts of buoyancy & effect of weight distribution on floating bodies?
How to calculate the volume of sloped isolated footing?
What is the maximum allowable wastage in pouring of Ready Mix Concrete received at location with transit mixtures. Work scope includes both Direct Pouring & manual pouring.
1 Answers AKM Construction Management,
In beams why the depth is > width
1 cum brick work CM1:6 how many bricks sand cement required brick size 8"4"3"
what are the minimum compressive strength required for the concrete cube for different grades & different days .Please give me an answer.
Please tell me how to calculate the stiruup length for rectangular and circular coloumns
What is portland cement
what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?
DESIGN PROCEDURES OF R.C.C ELEMENTS
material calculations for I st coatplastering 16mm CM (1:5),second coat CM(1;3)4mm thick,pcc(1:4:8),RCC M20,lime stone masonry CM(1:6)
What are the advantages and disadvantages of Solid blocks over clay bricks in civil constructions ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)