how to calculate sand, cement quantity for plastering (1:5)? what"s the formula?
Answers were Sorted based on User's Feedback
Answer / rajarshi basu
Let Area to be plastered=100 m^2
& Thickness of plaster= 12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+5=6
For 12mm plastering in 1:5 cement:sand mortar mix,
1)Cement required= 1.92/6= 0.32 cu. m
No. of bags of cement= 0.320/0.0347=9.22 bags
>>9 bags(say)
Kgs of cement required=9 x 50= 450 kg (approx)
2)Sand required= [1.92 x (5/6)]= 1.60 cu. m
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
| Is This Answer Correct ? | 269 Yes | 26 No |
Answer / sandeep tv
let Area to be plastered=100 m^2
& Thickness of plaster= 12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+5=6
For 12mm plastering in 1:5 cement:sand mortar mix,
1)Cement required= 1.92/6= 0.32 cu. m
No. of bags of cement= 0.320/0.0347=9.22 bags
>>9 bags(say)
Kgs of cement required=9 x 50= 450 kg (approx)
2)Sand required= [1.92 x (5/6)]= 1.60 cu. m
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
| Is This Answer Correct ? | 60 Yes | 12 No |
Answer / ashwin
cement:sand= 1:5
for 1cum= 1/6
=0.166
so cement for 1 cum=0.166cum
but volume of 1 cement bag is=.033cum
bag required per cum is=.166/.033
=5 bags
sand required is=0.166*5
=0.833 cum
| Is This Answer Correct ? | 100 Yes | 58 No |
Answer / yogesh khandelwal
Let Area to be plastered=100 m^2
& Thickness of plaster= 12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+5=6
For 12mm plastering in 1:5 cement:sand mortar mix,
1)Cement required= 1.92/6= 0.32 cu. m
No. of bags of cement= 0.320/0.0347=9.22 bags
>>9 bags(say)
Kgs of cement required=9 x 50= 450 kg (approx)
2)Sand required= [1.92 x (5/6)]= 1.60 cu. m
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
| Is This Answer Correct ? | 13 Yes | 4 No |
why should we have to take 20% of wet mortar & 1/3rd of Dry mortar......is there eny code for that...or plz tell me where it coms from......plz clear me ....
| Is This Answer Correct ? | 12 Yes | 3 No |
Answer / adz
1:5 proportion for (1)cement @ 40kg): (5)sand @ 33 kg(S.G
@2.6) gives you approximate volume of 0.142 cubic meter.
if you want exact volume, provide the specific gravity of
your materials and include air content and water for your
volume...
| Is This Answer Correct ? | 8 Yes | 0 No |
Answer / abrar
c:m ratio for plastering (1:5) for 1 cum
sand 1cum = 1.25cum .... constant in all ratios
cement 1cum = 1.25 x 1440
------------ = 360 kgs = 7.2 bags
5
| Is This Answer Correct ? | 16 Yes | 12 No |
Heat gain in buildings is best resisted by
6 Answers AIEEE, B Arch, JMC Projects, Unique Dream Builders,
For the construction project what capital cost has to be taken in consideration?
how to know 28 day strength of concrete knowing 3 day or 7day strength of concrete???
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?
which has high coefficient of discharge venturimeter or orificemeter
Coverage of 25mm.thick ratio of 1:4 cement mortar?
How much wastage we considered for cement
material cost to cast m20 grade rcc
In csae of hume pipes NP stands for Non Pressure bur what does it really mean?
please help me to find a mix design ratio for M40....
what is the bearing capacity of hard rock
what is the difference between highway and motorway?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)