how to calculate sand, cement quantity for plastering (1:5)? what"s the formula?
Answer Posted / sandeep tv
let Area to be plastered=100 m^2
& Thickness of plaster= 12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+5=6
For 12mm plastering in 1:5 cement:sand mortar mix,
1)Cement required= 1.92/6= 0.32 cu. m
No. of bags of cement= 0.320/0.0347=9.22 bags
>>9 bags(say)
Kgs of cement required=9 x 50= 450 kg (approx)
2)Sand required= [1.92 x (5/6)]= 1.60 cu. m
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
| Is This Answer Correct ? | 60 Yes | 12 No |
Post New Answer View All Answers
how to calculate number of bitumen for road asphalt
How do we test on design and style in a software?
a) Difference between Ghol , Chimney & fly ash bricks b)Floor to floor height is 3m , rise=15cm , tread 20 cm , how to design staircase means steps landing
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
What are the advantages of cad?
How to do base isolation using ETABS software?
Types of column foundation and how to calculate its steel quantity.
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
How to calculate sand , cement quantity for 23mm thk brick work(10x10)
660 square fit two story house make totally how much cement, sant, brick,aggregate, steel totally how much need
How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit
Why are steel plates inserted inside bearings in elastomeric bearings?
For the symmetrical continuous beam shown in figure, Prestressed with a force P = 1500 KN along parabolic curve as shown, compute the extreme fiber stresses over the central support for the uniformly distributed load of 24 kn/m. Use load balancing method.
What glue is least sticky?
what is Short bored pile foundation.