Answer / praman srivastava
the wastage for steel & cement for mainly consider for
handling , tranpotation & workmanship & in case of steel
wastage consider for cutting bending & scrap during
work.Approximate 3% wastage consider for above as per CPWD
Norm.
| Is This Answer Correct ? | 44 Yes | 10 No |
Answer / sjtbehera
incase of cement-3%
reinforcement above 20mm-5%
20mm and below-2.5%
| Is This Answer Correct ? | 27 Yes | 9 No |
Answer / prabhakar trimukhe
i think 2% of quantity of the material
| Is This Answer Correct ? | 2 Yes | 3 No |
How you can use different dimension tools in cad? What are the different dimensions available?
Define the various stages of the project planning process in construction.
what is diffreant types of water proofing chemical tell me please
what is a pretension and post tension with an example
use ofr concrete as per grade ?
can any one explain bar bending schedule of bems and columns and slabs ??
How can effect the Floor tiles if water absorption value is higher than 0.5%?
Wat is meant by Aecron brick?
how to decide the column size and dia of the bar
How steel required for 823 sqm of flooring work in 150mm c/c in single jali?
minor loss due to sudden contraction 1>flow contraction 2>Expanssion of flow after sudden contraction 3>cavitation 4>boundry friction
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)