Please explain about FAT? What is the difference between
FAT and SAT?
Answers were Sorted based on User's Feedback
Answer / manoj
FAT = Factory acceptation test
SAT = Site acceptation test
when any company going to install new instrument control
system,they have to test how its working ? In the FAT shop
they will do configuration setting for all instrumet loops.
according to configuration the system providor will do
function test by simulating signals.
but during the SAT they will check all function with real
Input signals.
| Is This Answer Correct ? | 37 Yes | 2 No |
Answer / ajay
FAT: it is the acronym of Factory acceptance test i.e.
Tests performed under simulated conditions at
manufacturer's place witnessed by approving authority
client/End user.
FAT is performed to check the correctness of the system
being supplied. FAT covers all checks over hardware,
interfaces, logics & control loops and system configuration
as per the procedure defined in FAT document.
FAT is performed for Control/DCS & PLC panels.
SAT: it is the acronym of Site acceptance test i.e. tests
performed under live signals received from instruments
installed in plant during the actual commissioning of the
system at site/ end user's place. During SAT, all live
signals are checked and individual control loops & logics
are performed accordingly.
Once all individual loops and logics are checked, then only
plants process is left to run through control system itself.
| Is This Answer Correct ? | 20 Yes | 1 No |
FAT: It will be conducted at System Supplier's place with
presence of EPC and End user.They will check the
functionality of Control loops and logics with use of
Simulators.Third part devices will also physically
connected to the system supplier and functionality will be
checked and corrected.
SAT: It will be conducted at End user's place.Here field to
system will be checked and corrected.
| Is This Answer Correct ? | 13 Yes | 0 No |
Answer / visakh
hello shanker
these to tests are nothing but to check all the instruments
or materials are in good condition(means damaged or not)
| Is This Answer Correct ? | 1 Yes | 11 No |
hi i want sov loop cheak from consol to field the operater given status to sov still no change, but MR room to sov ok so whats a problem and alreasy cheak all conection ok ?
what barrier is used in process industry.
3 Answers ADMA OPCO, Process Industries,
i want to make project on process control using plc.please give me idea about this.
tell about various protocols used in different plcs
what is the formula for calculating milliampere at different pressure points for eg 4-20 ma = 3-15 psi but if i have to check the ma at 4.6 ma?
I want to measure and control level in tank of size 10*5 filled with gasoline, so plz give me the solution with clear details. how to select transmitter and sensors.
I have seen the Temperature element (T/C & RTD) installed in process line on 45 degree position, Why? What it mean? How many types of tapping position for temperature elements?
how to measure temperature from resistance of rtd?and how to measure temp from voltage of thermocouple?is there any formulas?
What is capacity of impulse line tube ...answer in psi
What do you do as a Engineering person EPC for Sizing&Selecting Control Valve?
A RANGE OF TRANSMITTER IS (0-400)B mm abs what is "B"?
how to calculate the total flow in square root
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)