How to schedule counter base maintenance plant for DG in
power plant that need 800hr per month maintthis
steps i followed.
1)i have created meas pt with counter (IK01) created meas
document IK11 then schedule thru IP10.
but not getting due order list in ip24.
can any one help me by telling exact cycle.
thanks in adv.
Answers were Sorted based on User's Feedback
Answer / maria terence
Hi
First of all, you cannot get 800 hrs per month...
For counter based... it will schedule in two days... like..
days and hours... but.. if u schedule in IP10..it wil take
the annual reading and schedule the dates.. So.. if the
running hrs didn't reach, but the date reached... so.. it
will open a order...
Give the annual reading according to the running hrs of the
DG.. then u will get
Is This Answer Correct ? | 17 Yes | 2 No |
Answer / patil kiran
Ist if you want u can make strategy plan with counter base
for that make strategy thro IP11 ( 200,400,600,800 Hrly
operation PM check list & attach Taskl list to PM plan)
iindly two type of schedulling one is manual other is
automatic ,. make the program standard RISHTRA20 THROUGH
IP10 dead line monitoring with varient for particular plan
on periodic basis i.e. every day night or weekly basis.
that sit you will get PM order through automatic
schedulling.
if anybody wnt to comment on above plz mail me.
Is This Answer Correct ? | 8 Yes | 0 No |
Answer / riyaz
in one month we can run Dg 24 hrs
we get only 720 hrs as per ur question suppose dg will run
800 hrs follow the below steps. just imagine.
create single cycle plan.
crate equipment(DG)
Assign task list for this equipment
Create measuring point with ik01
create measuring document with ik11
Create plan with ip01 (for every 800 running hrs)
scedule the plan with ip10
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / kalyan
please check the scheduling period for counter plan
Is This Answer Correct ? | 0 Yes | 0 No |
What is difference between system status and user status?
What is difference between corrective maintenance and preventive maintenance?
What is sap plant maintenance?
What is business purpose of equipment bom?
What is equipment master record?
Why would you maintain functional location bom?
Which goods movement is used to issue material with reference to a reservation triggered from a maintenance order?
What is maintenance plan? Name all types of maintenance plans.
What is purpose of technical id field in equipment master data?
Is it possible to assign user status to a sub-operation in maintenance order?
What are the activities of a sap pm?
I want to learn SAP PM. Can anyone tell me the sequence. I mean the topics in sequence. I have the material