How much quantity of Cement and Sand required for Cement
Sand Ratio of 1:1 and volume of pile is 0.61 m3
Answer Posted / sjtbehera
8. Volume of pile -.61m³
If you given cum your ratio is 1:1:2 not 1:1
Total ratio=1+1+2 = 4 so cement = .61/4=.1525m³= 4bags
Sand=.1525cum
Agg.=.1525*2=.305m³
| Is This Answer Correct ? | 5 Yes | 20 No |
Post New Answer View All Answers
what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?
What is change order request?
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
Why reinforcement done in shorter span in two way slabs
if 20mm aggregate is coming by weight 25 ton in a 10 wheeler hywa ,then what will be total volume of aggregate in cubic feet.
what is tension column?
How to determine thee cut length for steel reinforcement bars in R.C.C design
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
Define What is Civil Engineering?
what is the difference between replacement of cement by groundnut shell ash
why & what is perchatage we are using fly ash in concrete?
Would you cause a 55-gallon drum of water to weigh more by climbing in?
For the calculation of bearing pressure below the footing, to know whether it is below the safe bearing pressure of the soil, the unit of RCC below ground level to be taken is 25 KN/m3 or (25-15)KN/m3, where 25 is the unit weight of RCC and 15 is the unit weight of soil and whether the weight of backfilling to be taken?
what mean By core Billing
Prepare a Schedule for a Highrised building from starting stage to Handover?