How much quantity of Cement and Sand required for Cement
Sand Ratio of 1:1 and volume of pile is 0.61 m3
Answer Posted / sjtbehera
8. Volume of pile -.61m³
If you given cum your ratio is 1:1:2 not 1:1
Total ratio=1+1+2 = 4 so cement = .61/4=.1525m³= 4bags
Sand=.1525cum
Agg.=.1525*2=.305m³
| Is This Answer Correct ? | 5 Yes | 20 No |
Post New Answer View All Answers
What are the advantages of cad?
I am practising engineer. I am searching for tutorial of RCC T Girder design Example in staad pro.Do anybody has this?please help
what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????
construction workers how much time take one work or qty
how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
Which is the best book for building construction?
How many cum of 9.5mm stone in 1 ton ?
What is the difference between a wood shake and wood shingles?
In block work seawalls what is the purpose of slip joints?
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
if the nitrates more than 45mg/l in water lead to disease then what is it called
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
what is cement wastage percentage in NHAI ROAD WORKS
Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)