How much quantity of Cement and Sand required for Cement
Sand Ratio of 1:1 and volume of pile is 0.61 m3

Answer Posted / s.r.shiradhonkar

vol of pile is 0.63 cum
Material required
Metal (0.80 cum/cum of concrete)i.e 0.8*0.61=0.488 cum
Sand (0.40 cum/cum of concrete) i.e 0.4*0.61=0.244 cum
cement(0.40 cum/ per cum), (as cement sand ration mentioned
1:1). cement required= 0.4*.0.61=.244 cum. 1bag of 50 kg
have volume 0.035 cum. there for bags required=0.244/.035=
7 bags.

S.R. Shiradhonkar
Amarawati.

Is This Answer Correct ?    6 Yes 7 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Under what circumstances should pot bearings be used instead of elastomeric bearings?

813


what is the clear cover for shearwall?

1165


Describe the advantages and disadvantages of using plastic and timber fenders?

771


How is make concrete cube?

811


explain the rale of the government in the construction industry

2026






What is the difference between one-way slab and two-way slab?

753


In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.

1918


please briefly explain calculating or estimating steel quantity for a RCC column?

1556


I am a civil engineering student and going to attend interview in this week in an IT company.Will they ask me questions about my area of interest or cs

2165


Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards

1685


Define a polyline?

795


how much cement is consumed by a stone masonry wall 17.7m long,0.55m wide and 1m high

1549


Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??

2330


what is the Asfalt test?in road constraction..?

1729


 rcc floor to floor  4m. in column reinforcement where we provide lap in exact location.     

1588