How much quantity of Cement and Sand required for Cement
Sand Ratio of 1:1 and volume of pile is 0.61 m3
Answer Posted / dushyant bansal
For 1:1 Cement sand ratio
total volume of either will be same as the ratio will be
1:1
and Sand will cover about 80% volume hence 0.8*0.61=
0.488cum
and same vol of cement.
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
Rate analysis of Vitrified tile in cement mortor 1:3
I have an plot with area 35*47 = 182.77 sq yards. Out of this iam planning to construct house with 1350 sqfeet each floor .iwanted to build a G+2 house.Need cost estimation for each item
how will remove spiderweb cracking in plaster ? what the reasone of make it ?
What is the force exerted by the tacoma narrows bridge?
How to make a c++ program that converts any base to base 10?
How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?
What is min thickness,min grade of conc & age of PQC ?
what are the layers of the national and heir aprox thickness??
How much material is required for constructing a 2 Lane 2Km rigid pavement road
it is possiblee to produce concrete with out cracks...
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
why demand factor less then 1 ?
115mm thickness brick work how to required mortar
WHAT IS YOUR EXPECTED SALARY?
How to calculate canal slope curvature qty!