Explain handled go live activities-Dry run,Cut over
activities & post go live Support
Answer / dantham conpolwedson
Dear All,
The sequence of the activities given is as follows,
Dry Run
Cut Over
Go Live
Post Go live Support.
In Dry Run the business activities that are configured in
system are given to user, for testing and evaluation,
training etc. In this case the existing system runs
parallel to the new system, so as that no business are
hampered, as well as accurate results are achieved.
In Cut Over, a call is taken from both the point of view,
i.e. system and business, that old system is to be cut off
and new system will take over the activities. However few
business tend to run both the system parallel till a
confidence level is build, and end results are same as both
the systems are concerned. But in Cut over, user does not
expect too much from the old system.
In Go Live, the old system is stopped, stock are taken into
the system, accounts values are books of accounts are same
as old system, from where the new system will take over
from the old system, old system may refer to legacy data
for references but, so far as the current activities are
concerned, they take place in the new system, the old is
for reference only.
Post Go live Support, this involves support activities
after the Go Live has been successfully done. This may
involve, new developments, reports.
Please correct me, if there is any mistake in the answer
given.
Regards,
Dantham Conpolwedson
Is This Answer Correct ? | 29 Yes | 1 No |
what is the price list and condition update in pricing
What do you mean by Alternative Calculation Type & Alternative Base Value in Pricing? Give definition of above terms and then Give as many examples as possible from your real time project data? Plz give more emphasis on explanation, procedure and real time examples from your project data. Please answer this question asap.... Its Urgent.... Looking forward for your express reply...I have interview within 1-2 days. So, give reply to this query asap.. I would be very grateful to you for your timely help.Thanks in advance. Regards
In 3rd party sales, how do we know whether the vendor has delivered the full order quantity to the customer? If we create a sales order for 100 qty and the vendor delivers 50 qty but sends an invoice for 100 qty, how do we know how much qty was actually delivered by the vendor?
3 Answers Infosys, Innovative Solutions, Kelloggs India,
Hi can some one post on interview questions& answers on CIN relevance to sd
What is material account assignmanr group , Paramater for determining right GL account?
I have a problem of invoice printing, in a particular period some invoices were printed double. Please let me know how can i find "HOW MANY and WHICH invoices were printed double in SAP system.
Explain the Steps to setup a route?
Fullform or Longform of ERP?
What is document type?
What are the different billing process u have done in your project.
What is the path to define condition type in sap for pricing?
how is shipping point determined?