How can PS be linked to COPA? How will the settlement take
place in this case (when PS is linked to Controlling
through COPA)
Answers were Sorted based on User's Feedback
Answer / kokopatil
How can PS be linked to COPA?
Sttlement Rule assigned to account asigned WBSE. In this
rule you define "RECIEVER" as PSG - Profitablity Segment.
This links PS and COPA.
How will the settlement take
place in this case (when PS is linked to Controlling
through COPA)
All the cost posted in this WBSE are pushed to PSG via
periodic settlement.
Is This Answer Correct ? | 7 Yes | 4 No |
Answer / co consultant
Settlement will take place via profitability segmenet .
Level 1 WBS should have settlement rule define to be
settled to PSG and level 2 WBS should be settled to
superior one WBS element .The main one level 1 WBS/ Project
will be settled to PSG , and variance will be posted to
COPA .
Is This Answer Correct ? | 5 Yes | 4 No |
Answer / harish kumar
COPA is profitableity analysis that groups and revenues according to value fields and costing based valuation aproaches.. when your create ALLOCATION STRUCTURES (OK06) in U difne the target cost elment (primary cost and secondary cost) for setlement of project in sap ps module.
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / ramakrishna
go to settlement profile,put the settlement receiver as PSG(Profitability segment).Here is the linkage between PS and COPA. Assign this sett. profile to the project profile and run the CJ88. Value flows from PS to Controlling. Of course you have to create settlement rules for WBS element.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / p.chaithanyavikram
Hi All
While doing Billing, The sale order is not a cost object then only the values should go to COPA. If Presupposes we are doing Result Analysis, RA nothing but Progress. So values wont go to the books of accounts, that time values will go to the Controlling Object (COPA).
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / lakshmi
Through actual settlement process we can transfer data from
ps to copa
Is This Answer Correct ? | 4 Yes | 7 No |
Answer / ashish
CCA/ PCA will give actual costing of project that may led
to Project cost (Planned/actual)
Is This Answer Correct ? | 1 Yes | 8 No |
What is project type?
You want to update the progress in wbs elements. How would you do that?
How and where do you control the budget for the project & what is the menu path?
Is there any way by which we can lock two specific wbs elements say overheads and other expenses, so that the user cannot release pr?
What is effort variance?
How is the budget for the project controlled? Tell the menu path for the place where it is controlled.
Explain the organizational structure of sap-ps module. List the parameters of project system.
What does procurement administrator involve?
How to set field status of wbs as mandatory, (wbs element, and ntw) ?
How should changes controlled?
What do you understand of pareto (80/20) principle/analysis?
Forming a team, developing the team and improving knowledge are direct responsibilities of the project manager, do you agree?