Answer / sapsd
It is possible to carry out two different pricing
procedures at sales order level and billing document level.
The pricing procedure is determined in a document on the
basis of the following parameters:
1) Sales Area (Sales Organisation+Distribution
Channel+Division)
2) Customer Pricing Procedure (Defined in the Customer
Master)
3) Document Pricing Procedure (Defined in Document Type
Customisation)
For a sales order and a billing document which corresponds
to the same sales order, the document pricing procedure can
be different and hence different pricing procedures can be
determined.
Also, in the copy control from sales order type to billing
document type, the price type for item category should be
set to "B" i.e. carry out new pricing.
Is This Answer Correct ? | 17 Yes | 3 No |
Answer / hemraj
as you know pricing procedure is determined by
sales area + doc. pricing pro. + customer pricing procedure
document pricing procedure will come from sales document
types and Billing Types.
customer pricing procedure will come from customer master
Between the sales document and billing document the only
factor that could change is the document pricing procedure
If they do not differ the same pricing procedure would be
used and the control would be as per the configuration
given in the copy controls.
If they differ then new pricing procedure determination
will be carried out but for that in copy control we need to
maintain PRICING TYPE AS B carry out new pricing else it
will give you error saying pricing procedure could not be
determined
Is This Answer Correct ? | 5 Yes | 0 No |
This happens when you are ordering before budget & you are billing after budget and you want to include new tax condition type in the pricing procedure.
SAP SD pricing procedure determination is by sales area, customer PP, document PP.
If you change document PP it will determine new pricing procedure.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / rohit
Pricing procedure is determinded by the following criteria
Sales Area comprising of Sales organisation, distribution
channel and Division
Document Pricing procedure
Customer Pricing procedure
On the detailed screen for the document type there is a
field called document pricing procedure where you maintain
A, B or watever desired
So similiary for the Billing document u maintain the
Document pricing procedure.
While doing the assignemtn of the pricing procedure you can
maintain it differently for both of the Sales order and the
Billing document
Is This Answer Correct ? | 1 Yes | 3 No |
Answer / ashraf
No Pricing Proc. can not possible to two level, Pricing
Proc. can be possible either sale doc. level or Billing
Doc. level.
ASHRAF
ashrafsheikhsap@rediffmail.com
Is This Answer Correct ? | 1 Yes | 3 No |
Answer / peeyoosh
Normally it remains the saem as that at Sales order level.
However, if you are maintaining a pricing procedure at both
Sales order and Delivery levels, then the pricing procedure
at Billing level can be a combination of both, thus
differing the one at Sales order level.
Also you can carry out settings in system to keep the
values of condition types same at both levels and different
at both levels through setting in copy control.
Is This Answer Correct ? | 3 Yes | 12 No |
What are the two editor modes in which we can configure the sap transport routes? : transportation management
Is it possible to automate output processing?
You want to list all condition records for a certain material or a certain sales organization. How would you do that?
what is puchase life cycle?
what is transfer order?
what were the setting had to be done when stock was send through company itself to customer instead of vendor in third party sales secenerio.
i created delivery document 1000 qty and made batch split in 4 line item as 250 each, while doing Invoice showing 4 line item. i need make it one line item of 1000 Qty. In VTFL, what changes has to be made?
What is a fiscal year and fiscal year variant?
Could anyone please share SAP SD Support Project's Priority tickets with detailed solutions ?
while create sales order, user cannot change ship to party address in sales order level how to controled ?
Hi I am srinivas. I trained sap sd course. I know all transaction codes and tables as per bookish knowledge. But I don't know which t-codes and tables we use in real time. So i want to know the t-codes and tables in real time. pls help me. Thank u. Srinivas
how does company knows that vendor deliver the goods to the customer in third party sales process