How to plan the time estimations for QA cycle ?
Answers were Sorted based on User's Feedback
Answer / raj
Study requirements
Prepare test plan and identify the functionalities to be
tested in cycle
Identify the test approach
Identify test points and complexity of each test point.
Calculate the time required by one resource to complete one
function and based on this complete the estimation. Plan
the cycles based on the type of testing for
example :functional/system testing and then regression and
UAT.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / editor
For estimation
there are different kinds of estimation techniques.
1. Expert based- needs to derive FP's
2.Experienced based' Based on Previous project exp
3. WBS - break down structure..
| Is This Answer Correct ? | 2 Yes | 1 No |
What are the different artifacts you refer when you write the test cases?
What test strategy followed in your project?
What if the application has functionality that was not in the requirements?
'configuration related errors' in testing means what?
What is Comparision Testing?
What documents QA team needs from Development to orginize a QA process
Diffrence b/w compiled module and shared repository?
hey, i recently attended 2 interviews and they asked whether I used qamonitor of softsmith. any help on what it does?
What is the need of test plan document?
Have you ever managed writing the test cases without having any documents?
What is the difference between bottom-up and top-down integraion?Which is effecive.
What are test documents and what it includes?