What are settlement rules?
Answers were Sorted based on User's Feedback
Answer / nicola k
In SAP most cost objects - other than cost centers - must be
"settled" at period end. By means of the settlement the
costs incurred for the cost object (project, internal order,
...) are debited to other cost objects and/or G/L accounts.
The settlement rule, a table maintained in the cost object
master data, describes to SAP how the costs will be settled:
receivers, percentages, full/partial, etc..
Cost are settled when the user starts the settlement
procedure at period end.
Is This Answer Correct ? | 54 Yes | 5 No |
Answer / satish
Settlement rules are nothing but settling the account for a
cost center.Which WBS are account assigned the cost of
corresponding WBS should be settled to the respective cost
center assigned for that WBS.Settlement rule is assigned in
settlement profile in which you will define (like assect)
the rules of settlement.
Is This Answer Correct ? | 26 Yes | 14 No |
What are processes and process groups?
Can anyone post the SAP-Project systems interview questions.
what do activities mean?
What is a critical path in schedule network diagram?
What is effort variance?
What is the organizational structure of ps module?
What is Project Management?
5 Answers A1 Technology, Aktiv, T systems,
How to calculate WIP in PS for all wbs pertaining to that particular project? Any specific T code in ECC 6.0?
what is difference between capital project and customer project in period-end closing
What is standard project structure?
Explain the team forming process?
What is wbs?