Answer Posted / nicola k
In SAP most cost objects - other than cost centers - must be
"settled" at period end. By means of the settlement the
costs incurred for the cost object (project, internal order,
...) are debited to other cost objects and/or G/L accounts.
The settlement rule, a table maintained in the cost object
master data, describes to SAP how the costs will be settled:
receivers, percentages, full/partial, etc..
Cost are settled when the user starts the settlement
procedure at period end.
| Is This Answer Correct ? | 54 Yes | 5 No |
Post New Answer View All Answers
Are there any positive aspects of the risk identification process?
Define project definition?
What is wbs?
Do you think professionalism and integrity are essential qualities of a pm?
What are time & material contracts?
What does scope management involve?
What is the accounting and logistical information that gets defined with a project definition?
What are the important aspects of a hr plan for the project team?
How will you define a project?
You want to lock two wbs items say overheads and other expenses so that the user can not release pr. How would you do that?
What is effort variance?
You want to update the progress in wbs elements. How would you do that?
How does coding mask affect the project? Tell the menu path for the location where it is created.
Differentiate between validation and substitution
Is there any way by which we can lock two specific wbs elements say overheads and other expenses, so that the user cannot release pr?