Answer Posted / nicola k
In SAP most cost objects - other than cost centers - must be
"settled" at period end. By means of the settlement the
costs incurred for the cost object (project, internal order,
...) are debited to other cost objects and/or G/L accounts.
The settlement rule, a table maintained in the cost object
master data, describes to SAP how the costs will be settled:
receivers, percentages, full/partial, etc..
Cost are settled when the user starts the settlement
procedure at period end.
| Is This Answer Correct ? | 54 Yes | 5 No |
Post New Answer View All Answers
What is the impact of coding mask on the project and where is it created (menu path) ?
You want to define special characters for projects. What t-code and menu path will you use?
What is project type?
Explain planning profile.
How does coding mask affect the project? Tell the menu path for the location where it is created.
What is a sow?
Are there distinct kinds of activities in a project?
How to set field status of wbs as mandatory, (wbs element, ntw)?
What is project definition?
a new comer joined in ps consultant role, whats his first job and duty? how he can explain the project details to others? i requesting all the experienced consultants please post the your real time faced attitude and job based problems for getting the morality from you people. please post the answers
What are time & material contracts?
Explain time profiles.
What is the difference between validation & substitution?
What is the accounting and logistical information that gets defined with a project definition?
You want to lock two wbs items say overheads and other expenses so that the user can not release pr. How would you do that?