Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Thirty men take 20 days to complete a job working 9 hours a
day. How many hour a day should 40 men work to complete the job?

(a) 8 hrs
(b) 7 1/2 hrs
(c) 7 hrs
(d) 9 hrs

Answers were Sorted based on User's Feedback



Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / sneha aitha

30 men-20 days-9 hours
40 men-   ?   -   ?
so m1 d1 h1 = m2 d2 h2
    30*20*9 = 40*d2*h2
 m1d1=m2d2
30*20=40*d2 then d2=15
 
30*20*9=40*15*x
 so then x=9hrs

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / vijayalaxmi uppala

m1*d1=m2*d2
30*9=40**d2
270=40*d2
d2=270/40
d2=6.75

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / aishu

30*9=40*t2
270/40=t2
ANS:6.75

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / praveen

30 * 20 * 9 = 5400 man-hours required to complete the job
Let x = no. hrs a day to do the same job (assuming in 20 days)
40 * 20 * x = 5400
800x = 5400
x = 5400%2F800
x = 6.75 hrs a day for 20 days to do the same job

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / jyosna

30 * 20 * 9 = 5400 man-hours required to complete the job
:
Let x = no. hrs a day to do the same job (assuming in 20 days)
40 * 20 * x = 5400
800x = 5400
x = 5400%2F800
x = 6.75 hrs a day for 20 days to do the same job
SO THE ANSWER IS 7HRS(approx)

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / yashwanth krishna

If the question is "how many hours should 40 men work to complete the same work done by 30 men working 9 hrs a day for 20 days?" then my answer would be,
if 30 men can finish a PIECE OF WORK in 20days then
1man's work will be 1/30for 20days and 1/30*20=1/600 is one man's 1 day work
then 40 men's 1 day's work is 40/600
and 40 men can do the work in 600/40 days=15days(working 9 hours a day)
which is 135hours(15*9)
if the work is to be completed in 20 days then 40 men should work 6.75hrs a day(135/20)

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / rahul parmar

30 x 20 x 9 = 5,400 man hours required for the job

You’ve given us 40 men and 20 days:

5400 / 40 / 20 = 6.75

So they would have to work 6.75 hours a day to complete the job.

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / muthuganesan

while increase the men, the working days will be decreased,
but the working hours would be the same, nobody decrease the
working hour in their organization.

so answer would be a) 9 hrs

Is This Answer Correct ?    1 Yes 3 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / gajendra

30*20*9=40*20*T2
t2=(3*9)/4=6.75=7
so currect answer is 7.

Is This Answer Correct ?    4 Yes 10 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / fox

they should still work 9hr days and get the job done
quicker!

Is This Answer Correct ?    9 Yes 41 No

Post New Answer

More General Aptitude Interview Questions

burns caused by steam are more severe then burns by hot water.wahy?

1 Answers  


The price of raw materials has gone up by 15%, labour cost has also increased from 25% of the cost of raw material to 30% of the cost of raw material. By how much percentage should there be a reduction in the usage of raw materials so as to keep the cost same

0 Answers   Cap Gemini,


What can six men do at a time which six women cant do?

7 Answers   TCS,


there are 27 coins in which one is heavier than rest(all equal weight). how many measurements are needed to isolate that odd one.

0 Answers   Verifone,


I am applying for vizag steel plant management recruitment for 2009 please can anybody send me the pattern of the written test paper

31 Answers   Salem Steel Plant, Steel Plant, TATA, Vizag Steel, VSP,


WHAT IS CALLED FLYING IN AEROPLANE?

4 Answers  


Under CICS, multitasking achieved by what method? A. virtual paging. B. task switching. C. priority numbering, D. pseudo conversational

1 Answers  


A sales person multiplied a number and get the answer is 3, instead of that number divided by 3. what is th answer he actually has to get ?

0 Answers   Accenture,


A man spends half of his salary on household expenses, 1/4th for rent, 1/5th for travel expenses, the man deposits the rest in a bank. If his monthly deposits in the bank amount 50, what is his monthly salary ?

0 Answers   Mu Sigma,


which questions will be coming

0 Answers  


1.area of trapezium?

1 Answers  


A ship is away from the shore by 180 miles.A plane is travelling at 10 times speed of the ship.How long from the shore will they meet?

0 Answers   Infosys,


Categories