Thirty men take 20 days to complete a job working 9 hours a
day. How many hour a day should 40 men work to complete the job?

(a) 8 hrs
(b) 7 1/2 hrs
(c) 7 hrs
(d) 9 hrs

Answers were Sorted based on User's Feedback



Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / sneha aitha

30 men-20 days-9 hours
40 men-   ?   -   ?
so m1 d1 h1 = m2 d2 h2
    30*20*9 = 40*d2*h2
 m1d1=m2d2
30*20=40*d2 then d2=15
 
30*20*9=40*15*x
 so then x=9hrs

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / vijayalaxmi uppala

m1*d1=m2*d2
30*9=40**d2
270=40*d2
d2=270/40
d2=6.75

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / aishu

30*9=40*t2
270/40=t2
ANS:6.75

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / praveen

30 * 20 * 9 = 5400 man-hours required to complete the job
Let x = no. hrs a day to do the same job (assuming in 20 days)
40 * 20 * x = 5400
800x = 5400
x = 5400%2F800
x = 6.75 hrs a day for 20 days to do the same job

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / jyosna

30 * 20 * 9 = 5400 man-hours required to complete the job
:
Let x = no. hrs a day to do the same job (assuming in 20 days)
40 * 20 * x = 5400
800x = 5400
x = 5400%2F800
x = 6.75 hrs a day for 20 days to do the same job
SO THE ANSWER IS 7HRS(approx)

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / yashwanth krishna

If the question is "how many hours should 40 men work to complete the same work done by 30 men working 9 hrs a day for 20 days?" then my answer would be,
if 30 men can finish a PIECE OF WORK in 20days then
1man's work will be 1/30for 20days and 1/30*20=1/600 is one man's 1 day work
then 40 men's 1 day's work is 40/600
and 40 men can do the work in 600/40 days=15days(working 9 hours a day)
which is 135hours(15*9)
if the work is to be completed in 20 days then 40 men should work 6.75hrs a day(135/20)

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / rahul parmar

30 x 20 x 9 = 5,400 man hours required for the job

You’ve given us 40 men and 20 days:

5400 / 40 / 20 = 6.75

So they would have to work 6.75 hours a day to complete the job.

Is This Answer Correct ?    0 Yes 0 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / muthuganesan

while increase the men, the working days will be decreased,
but the working hours would be the same, nobody decrease the
working hour in their organization.

so answer would be a) 9 hrs

Is This Answer Correct ?    1 Yes 3 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / gajendra

30*20*9=40*20*T2
t2=(3*9)/4=6.75=7
so currect answer is 7.

Is This Answer Correct ?    4 Yes 10 No

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men ..

Answer / fox

they should still work 9hr days and get the job done
quicker!

Is This Answer Correct ?    9 Yes 41 No

Post New Answer

More General Aptitude Interview Questions

how many rivers are present in sindh?

1 Answers  


What do you know about Eclerx?

3 Answers   eClerx,


A boy scores 9 marks more than his friend in an exam and has 56% marks of the total of their marks. Calculate the marks scored by each of them.

0 Answers   CGI,


A person has his own coach&whenever he goes to railway station he takes his coach.One day he was supposed to reach the railway station at 5 O'clock.But he finished his work early and reached at 3 O'clock. Then he rung up his residence and asked to send the coach immediately. He came to know that the coach has left just now to tje railway station. He thought that the coach has left just now to the railway station.He thought that he should not waste his time and started moving towards his residence at the speed of 3mi/hr.On the way,he gets the coach and reaches home at 6 o'clock.How far is his residence from railway station.

0 Answers   Infosys,


If 32+24=100 what no. system is used?

4 Answers   3D PLM,






DATAINTERPRETATION ( 5 QUESTIONS 10 MINUTES ) DIRECTIONS(Q1-5) THESE QUESTIONS ARE BASED ON THE TABLE BELOW BRAND SALES IN JAN’99 PERCENTAGE CHANGE FROM EARLY YEAR K 7.5 12% L 10 3% M 22 -5% N 34 -10% O 16 -20% Q1). Sales of brand M in Jan’98 was what percentage of Jan’99 sales? a) 17.22% b) 24.58% c) 29.58% d) 21.22% e) Cannot be determined Q2). The ratio of sales of N in 1998 to O sales in 1998? a) 43 : 34 b) 13 : 10 c) 23 : 13 d) 31 : 22 e) 54 : 43 Q3). What is the proportion of sales of K, l and M to the total sales of all brands in 1999? a) 36.28% b) 26.19% c) 32.32% d) 12.23% e) 44.13% Q4). By how much have the sales of O and N together fallen in Jan’99 as compared to Jan’98 ? a) 32 b) 19 c) 22 d) 27 e) 21 Q5). Which brand faced the maximum changes in the sales from Jan’98 to Jan’99 ? a) K b) L c) M d) N e) O

1 Answers   Patni, Wipro,


In a certain code, ?acquisition or construction should be completed within three years? is written as ?three be or within should years construction completed acquisition?. How will ?interest paid on loan will be allowed for deduction? be written in that code ? (1) For will paid allowed loan on deduction be interest (2) For will allowed paid loan deduction on be interest (3) For will paid allowed loan deduction on be interest (4) For will paid allowed loan deduction be on interest (5) None of these

1 Answers   Infosys, SBP,


The perimeter of a rhombus is 52 units. One of its diagonal is 24 units.What is its second diagonals length?

0 Answers   Hexaware,


In June a baseball team that played 60 games had won 30% of its game played. After a phenomenal winning streak this team raised its average to 50% .How many games must the team have won in a row to attain this average? A. 12 B. 20 C. 24 D. 30

5 Answers   L&T,


WHY ARE YOU COMING FOR BPO

0 Answers   HSBC,


If the simple interest is 10.5 % annual and compound interest is 10 % annual, compounded annually, find the difference between the interests after 3 years on a sum of Rs. 1,000.

0 Answers   Essar,


if on a salary of rs."S" per month,one has to pay one tax of x rs. And a second type of tax of y rs then % of salary taken home is?

0 Answers   TATA,


Categories