Product Costing Run is over. Now If I add one more
rawmaterial for that material also it has to included & run
the cost. But it is not happening?
Answers were Sorted based on User's Feedback
Answer / gopid123
Its Simple u have to do CKR1 and again CK11n then CK24
Is This Answer Correct ? | 19 Yes | 1 No |
Answer / thakur
When we run the cost estimate, it updates the standard cost
of that finished material. If you want to update the
standard cost of the material including new raw material,
obveously you need to delete and re-run the cost estimate.
Otherwise, when you create the production order, there in
that cost calculation, real cost will be captured including
new RM and used for that production order and hence costing
data will be available for reporting and other purposes.
But standard cost will be effected only in the next costing
run, which may be falling in next month.
Is This Answer Correct ? | 4 Yes | 1 No |
Answer / nanduri k. prasad
Hi
The product cost run can be done only once in a month.
Hence, though you add one more material to bom the costing
run will not change.
Try to run it in the next month. it will be automatically
updated.
Is This Answer Correct ? | 3 Yes | 2 No |
Answer / rupesh
Your questoin is not clear.
But as per my understand if cost run is over that means
actual cost is calculated. so you can calculate std. cost
only for this month and you will have to wait for next cost
run.other wise you will have to reverse whole PC run and re-
run agian.
Is This Answer Correct ? | 4 Yes | 4 No |
Answer / sravan
cost estimate is done in CK11N but usually this will be
updated once in a month. or we have to reverse the cost
estimate for the current month and run it again.
Is This Answer Correct ? | 1 Yes | 3 No |
What is end user training
Once the Production order is created, how to change the BOM and routing in that order?
You want to create object dependencies in a bom for configurable materials? How would you navigate?
What is activity type and how it works in costing?
What is the use of QM control key?
What are dynamic actions? Give a few examples. What are it’s you used in them?
How did you configure the payscale structure?
Tell me important of the Production scheduling profile what are the things have to maintain in this profile
Explain how can you create production order without routing and bom?
Do you want to use one BOM to represent several similar materials (closed variant BOM)?
What are the common questions,asked at SAP PP Full time face to face interview?
What is the use of data in work centers?