cutover activities in sap
Answers were Sorted based on User's Feedback
Answer / brij bhushan sharma
PP Cut over activities are
1. Upload Bill of Material
2. Upload Work Center
3. Upload Routing
4. Open Production order upload
Is This Answer Correct ? | 4 Yes | 1 No |
Answer / mohamed moideen k
Cutover activity is to upload our master data from non-sap to sap server.
There are 3 types of cutover activities
1. LSMW - Legacy System Migration Workbench
2. BDC - Batch Data Communication
3. BAPI
Is This Answer Correct ? | 3 Yes | 3 No |
What is routing in sap pp?
What is the data you give in SOP
How to group employees for their allowances in payroll?
What are the levels of batch, explain batch determination process?
my scenario is repetitive manufacturing (REM) make-to-stock (MTS)production for sugar industry. What are the things, I have to customize for this scenario, to the PP point of view..
What are sequence, parallel, overlapping, splitting and where can we assign these
Hi All, In Repititive manufacturing during backflush we enter the production date and the batch. The classification for production date and Shelf life expiration date has been maintained in the material master. We have a characteristic "date of last goods reciept"which updates the characteristic value in the batch classification automatically from the production date entered in MFBF Tcode. Even though we have maintained the min shelf life and total shelf life the system does not calculate the remaining shelf life for the batch and does not update the value for shelf life in batch classification. Please suggest the procedure for updating values in batch classification for shelf life automatically from MFBF Regards, LN
Mention what are the t-codes for creating, changing and summarizing bom?
What is full form of EANs in Basic Data 1?
3 Answers Chembond Chemicals, Data Com,
What do we do in the realization phase?
what is pp cycle?
How many types of SOPs are there?