i hope that your calibration liquid you using is water[sg=1]. and your service sg=0.955.if so it is give you the output as per your observation
please make your calibration sg and service sg same value.
if you using service sg =0.95 and you using water for a measurement your maximuma span will be 95% and accordingly step change will effect.

Is This Answer Correct ?    0 Yes 0 No

I have one problem for masoneilan displacer type LT.I give some imformation in data shéet giv..

Answer / muhammad nasarullah khan

Hi Dear.
As you mentioned here taht transmitter's out put 0% and 100% (SPAN) is ok, but inbetween outputs having errror. So you are facing withe " LINEARITY PROBLEM "means out put is not linear , and that always should be linear. so go to linearity section by HART communicator ,hopefully I have answered your question.Regards

Is This Answer Correct ?    2 Yes 4 No

Post New Answer

More Instrumentation Interview Questions

how we will install a positioner ?

2 Answers   Descon,


why using negative supply for bentley nevada vibration system ?

0 Answers  


why direct mounted pressure transmitters is always installed with DBB ( double bleed block) valve in process line or top of the tanks ?

0 Answers  


defffrence between instruments and instrumentation

8 Answers  


An electronic p controller has an input range of 1-5v, and output range of 4-20mA, while testing a step change of 0.4 was applied at the input , the PB setting was 50% ,what should be the change in the output ?

1 Answers   Reliance,






Coal mill Instruments Equipments for cement plant And process diagram ?

0 Answers  


-/5A. What is the meaning and limitations of this in energy meter constant. It is a 3 phase LT Energy Meter. If this Energy Meter is connected through a CT of ratio 200/5 Amps, then what is the multiplying constant and how its will be calculated.

0 Answers  


1. what is modbus cable? 2. what kind of communication we are using for the interface of DCS, ESD and Third party cabinets? 3. What is serial communication and peer to peer communication?

0 Answers  


what is controlling card in dcs? how u measure dcs memory?what is bus in dcs?how u know dcs speed n ehternet speed?

0 Answers  


tion 0,50,100% equql to voltage formula?

1 Answers  


how can calibrate pressure transmeeter in the feild ?

1 Answers  


Can we use twisted pair cable instead of ethernet for communication?

1 Answers   Yokogawa,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)