for construction of 1 cum of brickwork what is requirement of cement, sand and bricks
Answers were Sorted based on User's Feedback
Answer / ravi
bricks 500
volume of mortar =0.2035 m3
dry volume of mortar =1.33*.2035=.306 m3
cement =.306*1/7=.0403 m3
sand=.306*6/7=.362 m3
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / nilesh jain
525 bricks ( with wastage ),1.35 bags of cement, 0.27 cum sand.
| Is This Answer Correct ? | 1 Yes | 2 No |
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?
What are advancements in civil engineering?
what are the cube & Sylinder strength of concret M20,M25,M30,M35,M40,M60 ,M75,M10 ,M15
For 25mm thick plastering how much sand and cement is used for 1 sft
1 Answers Assurance, Design Consortium,
How we can calaculate materials required for block work(1m3) block size 33cm x 20 cm x 17 cm, mortar 1:6
What are causes of cracks in outside plaster of a building and how we prevent it during constructions?
How much material is required for constructing a 2 Lane 2Km rigid pavement road
How we decide the depth and size of footing? Give a example?
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
why distibuters used in rcc slsb
What is soil enforcement?
how material can be calculate for brick work in 1:6
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)