for construction of 1 cum of brickwork what is requirement of cement, sand and bricks
Answers were Sorted based on User's Feedback
Answer / ravi
bricks 500
volume of mortar =0.2035 m3
dry volume of mortar =1.33*.2035=.306 m3
cement =.306*1/7=.0403 m3
sand=.306*6/7=.362 m3
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / nilesh jain
525 bricks ( with wastage ),1.35 bags of cement, 0.27 cum sand.
Is This Answer Correct ? | 1 Yes | 2 No |
If concrete fails in cube strength as well as non distactive test? what to do? for example grade of concrete is M35, cube strength is 26.1 n/mm2 after 28 days and non districtive test strength is 28.1 n/mm2 after 28 days. i am not distroying the rcc memeber.
what is the difference between volume and weight batching and which is better?
please give the detail design for the soring and shuttering for 8.5m deep excavation in the sandy soil for 25x10 rectangular streaches
how many types of admixters are used for C.C. Road works
1 Answers CADS Software, IVRCL, PSK,
how i get all type of short type question answer about civil engg
How to calculate cut bar length of steel reinforcement?
with out excell knowledge primavera is possible or not?
What is the unit weight of steel?
mix design ratio of M30 concrete
what is the grade of 1:2:1 concrete mix
yasser arfatcompleted his degree in civil from which university
How many bages of cement used in 1cft?and how we calculat sand and agregats