How to Determine the Quantity of Cement Sand , Aggregete
and Reinforcement Bars in 30 feet X 40 Feet and Height is 4
Feet .
Answer / prabu
1 feet = 0.3048 meter
30'*40'*4' = 9.144 *12.192 * 1.2192 meter
total volume = 135.92 meter cubic
1 bag cement = 50 kgs
unit wt of cement = 1440 kg/m3
density = weight/volume = 50/1440 = 0.0347m3
if concrete grade is M20 and ratio is 1:1:2
1+1+2 = 4
cement = 135.92/4 = 33.98
33.98/0.0347 = 979.25 bags
1 cement bag = 50 kgs, so
979.25 bag = 979.25 * 50 = 48962.53 kgs
sand = 1* 33.98 = 33.98 m3
aggregate = 2*33.98 = 67.96 m3
for slab = 0.7 -1% of concrete volume (reinforcement provided )
for beam = 1 - 3%
for column = 1 - 5 %
for footing = 0.8 - 8%
in this problem = 135.92 m3 concrete
for slab = 135.92 * 0.007 = 0.95m3 volume reinforcement provided.
ans =
cement = 48962.53 kgs or 979.25 bags
sand = 33.98 m3
aggregate = 67.96 m3
for slab = 0.95m3 volume reinforcement provide
| Is This Answer Correct ? | 9 Yes | 5 No |
Sir I am from jntuk R13 regulation...... Is there any chance to leave credits
which concrete grade has highest strenth and what is its comosition?
punj loyed and sapurjl palanjl
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
what is workability,define it?
Whta is the proportion of M30
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
what is the density of steel
10 Answers NGO, PWD, Sepco,
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
what is meant by skyscapers?
What are the uses of layer?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)