what is the formula for calculating the cement plastering for
a circular water storage tank.?plz help me thank you
aamirabdulsalam@gmail.com

Answers were Sorted based on User's Feedback



what is the formula for calculating the cement plastering for a circular water storage tank.?plz h..

Answer / n.ranjith kumar

(3.14*D)*Height of Tank (Inner or outer )

Is This Answer Correct ?    21 Yes 3 No

what is the formula for calculating the cement plastering for a circular water storage tank.?plz h..

Answer / sethu

what is the formula for calculating the cement plastering
for a circular water storage tank.?plz help me thank you
aamirabdulsalam@gmail.com



The Answer is - 2x22/7xrxh



r- for radius of the tank

h- height of the tank



while calculating inner area take inner radius of the tank



And for outside take outer radius of the tank



Regards,



S. Sethu

Is This Answer Correct ?    7 Yes 2 No

what is the formula for calculating the cement plastering for a circular water storage tank.?plz h..

Answer / chacko

it is easy man.
πD x h
π = 3.14 ( This is sethu answer 22/7 )
D = Diameter of the tank
h = Height of the tank

Is This Answer Correct ?    2 Yes 1 No

what is the formula for calculating the cement plastering for a circular water storage tank.?plz h..

Answer / pankaj balyani

3.14*d*height for sqm items
3.14*d*height*width for cubic mtr item

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?

0 Answers  


what is the m20 grade concrete ingredients?

2 Answers  


what is education Cess.

0 Answers  


hi frnds i hav got thro BHEL written exam..wat to prepare for intervw..guide me plz!!!!!!!!!!!!!

6 Answers   Bhel, HCC,


Define What are the uses of alloys in daily life and how are alloys made?

0 Answers  






What are some structures that are subjected to fatigue?

1 Answers  


how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .

0 Answers   CCCL,


Why was the empire state building made of steel?

0 Answers  


What is the density of pcc considered in structure design for load calculation

4 Answers  


why development length = 50D . why not 100D

0 Answers  


What is the strength of 1:6:12 mix?

0 Answers  


concrete coverings outside steel

13 Answers   Jain Housing, L&T, Supertech,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)