How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answers were Sorted based on User's Feedback
Answer / santosh singh
10 feet= 3.05m
area of plaster = 3.05 x 3.05 = 9.3 m2
(convert thickness of plaster into m divide by 1000)
volume of plaster = 9.3 x (10/1000) = 0.09 m3
quantity of cement = 0.09/1+5 =0.09/6 = 0.02 m3
as cement comes in bags of 50 kg therefore volume of one
bag cement = o.0347 m3 (exact)
(or it may be taken 0.034 or 0.035 m3)
no. of cement bags = 0.02/0.0347 = 0.58 bags (almost 1 bag
of cement required for plaster )
quantity of sand = 0.02 x 5 = 0.10 m3
this is exact calculation
you can add 30% extra for wastage etc.
| Is This Answer Correct ? | 688 Yes | 187 No |
Answer / srikanth
as per thumb rule 1:5 CM
3.04x3.04x0.01=.092416 cu.m
since wall is un-uniform ,increase by 30% ie
.092412 + .0277248= 0.120 cu.m
dry volume increses by 25% = 0.12 + .03 = 0.15 cu.m
total volume of mor= 0.15/6 = .025 cu.m
of cement =0.025x 1440= 36 kg cement
sand = 0.025 X 6= 0.15 cu.m
| Is This Answer Correct ? | 217 Yes | 96 No |
Answer / aijaz hussain, modi builders
Volume of Wet Mortar = 10 mm X 100 sft.
= 10/1000 X 100/10.76 = 0.093 cu.m.
Add 20% for depressions, joints and wastage
= 0.0186 + 0.093 = 0.112 cu.m.
Volume of Dry Mortar = 1.3 X 0.112 = 0.146 cu.m.= 5.154 cu.ft.
Cement required = 1/6 X 0.146 = 0.024 cu.m. = 0.7 Bag
Sand required = 5/6 X 0.146 = 0.122 cu.m. = 4.30 cu.ft.
| Is This Answer Correct ? | 117 Yes | 50 No |
Answer / abid nawaz
10' x 10' x 0.0333'
3.33 cft
Dry metarial in one cft = 1.27 cft
3.33 x 1.27
4.229 cft
sum of ratio = 1+5 = 6
quantity of cement = 1*4.229/6
= 0.7048 cft
volume of one bag = 1.25 cft
=0.7048/1.25
=0.56 cement bag
quantity of sand = 5*4.229/6
= 3.524 cft
| Is This Answer Correct ? | 76 Yes | 18 No |
Answer / sri
10'=3.04m
mix=1:5,
1/6=.1666+25%+30%=.71cu.m of cement
sand requires=3.5cu.m
plastering area=3.04x3.04x0.01=0.092416cu.m
| Is This Answer Correct ? | 125 Yes | 96 No |
Answer / manoj kumar moharana
cement mortar ratio is (1:5)
assume the area that we are going to calculate the plaster qty is,
L = 3.048 m
B = 3.048 m
given H = 10 mm = 0.01 m
hence the qty is = 3.048 x 3.048 x 0.01 = 0.093 cum
add 30% of the above qty for joints = 0.093 x 0.3 = 0.028
total qty = 0.093+0.028
=0.121 cum
add more 25% for dry volume = 0.121 x 0.25 = 0.03
total qty =0.121+0.03= 0.151 cum
no. of cement bags = 0.151/(1+5) =0.025 cum / 0.0347= 0.720 bags
= 1 apprx.( where as 0.0347 is the volume of 1 bag cement)
qty of sand = 0.025 cum x 5 = 0.125 cum
therefore mortar reqd. for 1:5 cement plaster is
cement = 0.025 cum = 0.720 bag
& sand= 0.125 cum
| Is This Answer Correct ? | 28 Yes | 5 No |
Answer / linu t mathew
Area to be plastered = 10'*10' = 100'
= 100/10.76 = 9.29sqm
(ie; 1 sqm = 10.76 sqft)
Thickness of mortar layer = 10mm = 0.010m
Volume of mortar required = 9.29*0.010 = 0.09cum
Add 15% for allallowance for calculation of surface and
wastages = (15/100)*.09 = 0.013 cum
Therefore, total volume of mortar required = .09+0.013 =
0.103 cum, say 0.10cum
Sand required for 0.10cum of CM 1:5 = 0.10 cum
Cement required for 0.10 cum of CM 1:5 = (1440/5)*0.10
= 288*0.10 = 28.8 kg
(ie; 1 cum of cement weighs 1440 kg)
| Is This Answer Correct ? | 42 Yes | 25 No |
Answer / naga
10'=3.04m
mix=1:5,
1/6=.1666+25%+30%=.71cu.m of cement
sand requires=3.5cu.m
plastering area=3.04x3.04x0.01=0.092416cu.m
| Is This Answer Correct ? | 17 Yes | 9 No |
Answer / ankit kumar
10 feet= 3.048m
Area=3.048*3.048=9.29m2
Thickness of plaster is 10mm or 0.01m
Volume of plaster = area*thickness
= 9.29*0.01
= 0.0929m3
Add 30% to fill up the joint,uneven surface etc
30% of 0.0929m3 = 0.027m3
The quantity of motar=0.0929+0.0279
=0.1208m3
Increase by 25% the total dry volume
25% of 0.1208m3=0.0302m3
Total dry volume= 0.1208+0.0302
= 0.151m3
For 1:5 sand motar.
quantity of cement=0.151/(1+5)
=0.02517m3
And for quantity of sand 0.02517*5=0.12585m3
Density of cement= 1400kg/m3
One bag of cement =50kg
Then volume of one bag cement=50/1400
0.0357m3
Now bag of cement=0.02512/0.0375
=0.67 bag i.e almost one bag
| Is This Answer Correct ? | 8 Yes | 1 No |
what is the allowable silt content in concrete?
how is the reinforcement is distributed in triangular slab
10 sqr in room reinforce concret so athu evvalavu wait thankum , atha eppati calculate panrathu
what will be the difference in compressive test results for a 150 mm cube, a 150 mm cylinder and a 300 mm cube
What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?
Explain Different types of raft foundation
Which one is the main bar in a square slab (2m x 2m)
How Many Cement Bags Are Used in 1 Sqm Area for Plaster????
8 Answers Era Infra Engineering, FactSet Systems, Indu Projects, L&T, Reliance, Rites,
curing of concrete why 7day's,14day's 21day's 28days
quantity of sand in cft in 1:6 cement sand mortar
1. if only 1 slab of a floor get sagged, how could be it repaired? 2. if any footing gives the cube result, after 28 days less than 16 n/mm2 in spite of 20 n/mm2 what are the remedies ?
what is the difference between rise and tread? what is its standered size? what is waist slab?what is the standered length of staire-case? also what is the angle between floor and landing?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)