HOW we can calculate the quantity of sand and cement for 1:4
plastering with a thickness of 12 mm..total area need to be
plaster is 985 sqm
Answers were Sorted based on User's Feedback
Answer / ashish
Area to be covered 985 sqm
thickness = 12mm
total cubic meter of work to be done = 985*.012 = 11.82 cum
cement sand ratio = 1:4
Cement to be consumed i Volume = 11.82*1/5 = 2.364 cum
Weight of Cement used = 2.364 * 1440 (density of cement) = 3404kg
no of bags used = 3404/50 = 68 bags (approx)
Is This Answer Correct ? | 4 Yes | 0 No |
Answer / eakub.molla
Total area=985m2
thickness of plaster=12mm=.012m
wet volume of plaster morter=985*.012=11.82m3
dry volume of morter=11.82*1.5=17.73m3
volume of cement=17.73/5=3.546m3
volume of sand=14.184m3
cement bag=3.54/.03542 bags
=100 bags.
Is This Answer Correct ? | 2 Yes | 0 No |
ACTUALLY I THINK
1 CUM = 35.315 CFT
12mm = .5"/ .039 feet /.012 M
so. 12 mm thick plastering = 1/ 0.012 = 83.33 Sqm
for 1 Cum cement required is in 1:4
1/4*1440 = 288 Kgs.
so, for 83.33 Sqm we need 288 kgs of cement & 288*4 = 1,152
Kgs. of sand multiply the amount with 985 & divide it by 83.33
3,404 Kgs. of Cement = 68 Bags.
Is This Answer Correct ? | 1 Yes | 0 No |
brother in your answer plz clearly define this step
10598.6*0.5=5299.3cft
1/5*1440=288 kg\
and why cement quantity is equal to sand quantity.?
Is This Answer Correct ? | 1 Yes | 1 No |
Answer / karthikeyan
1" = 25.4mm so,
12mm = 0.5"
total area = 985 sqm
1 sqm = 10.76 sqft
985 sqm = 10598.6 sqm
10598.6*0.5 = 5299.3 cuft(149.97 cum)
for 1 cum (1:4)1/5*1440 = 288 kg so
149.97*288 = 43191.36 kg
50 kg = 1 bag, so
863 bag cement is required
1 m^3 cement = 1 m^3 sand s0 863kg sand is
required
Is This Answer Correct ? | 0 Yes | 5 No |
Time required for curing of wall tiles before fixing
Define polar co ordinates.
pls give the grads of concrete and the ratios to the same
why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 days..
Hai, I have applied for APPSC AEE (I&CAD) post.I need previous AEE papers of civil engineering.I hope u will kindly consider this and send.
What are the strongest shapes in building?
how many cement in cubic feet of 40 kg bag white cement.
How many steel is require in one cubic meter area?
how to calculate sand, aggregate and cement in m25 concrete?
2 Answers CCL Products, Western Infrastructure,
What is green building?
Explain moment of inertia?
why there is need to provide shear reinforcement?give the basic reason?
9 Answers JMC, L&T, Power Grid,