HOW we can calculate the quantity of sand and cement for 1:4
plastering with a thickness of 12 mm..total area need to be
plaster is 985 sqm
Answer Posted / eakub.molla
Total area=985m2
thickness of plaster=12mm=.012m
wet volume of plaster morter=985*.012=11.82m3
dry volume of morter=11.82*1.5=17.73m3
volume of cement=17.73/5=3.546m3
volume of sand=14.184m3
cement bag=3.54/.03542 bags
=100 bags.
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
660 square fit two story house make totally how much cement, sant, brick,aggregate, steel totally how much need
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
When column of building is abutting the boundary line,then suitable footing advised is
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
Moisture content calculation for diff mix ratio's ??
how beam.coloum ,slab, footing are designed as per indian code.. detail procedure?
why demand factor less then 1 ?
how to compute slab reinforcements on step by step procedures??
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
TELL ME THE EQUATION FOR OGEE SPILLWAY
What are the steps involved in the concreting process?
What is Heavy Concrete & Normal Concrete
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
What is portland cement
1m square 20mm plastering how much of water need curing work