HOW we can calculate the quantity of sand and cement for 1:4
plastering with a thickness of 12 mm..total area need to be
plaster is 985 sqm
Answer Posted / k.l.b.srinivas
ACTUALLY I THINK
1 CUM = 35.315 CFT
12mm = .5"/ .039 feet /.012 M
so. 12 mm thick plastering = 1/ 0.012 = 83.33 Sqm
for 1 Cum cement required is in 1:4
1/4*1440 = 288 Kgs.
so, for 83.33 Sqm we need 288 kgs of cement & 288*4 = 1,152
Kgs. of sand multiply the amount with 985 & divide it by 83.33
3,404 Kgs. of Cement = 68 Bags.
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Formula for calculation volume of essentric footing
How can I make justification between using concrete grade c35 compare c37?
where i can get material costs on weekly basis
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
Why are pull-out tests performed for soil nails?
What are the applications of modulus of elasticity?
What tor stands for in tor steel?
What are new methods /technologies of pothole patching?
How to determine spacing of bars in slabs or beams
Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)
How can you produce desired alloys and discuss their applications in daily life.
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
foundation details for 25 ton weight Furnace on 2 supports and 2 tilters
What is the diff b/w ROAD TUNNEL & RAILWAY TUNNEL ??
Why are separation membranes used between concrete pavement slab and sub-base?