HOW we can calculate the quantity of sand and cement for 1:4
plastering with a thickness of 12 mm..total area need to be
plaster is 985 sqm
Answer Posted / mughal sab
brother in your answer plz clearly define this step
10598.6*0.5=5299.3cft
1/5*1440=288 kg\
and why cement quantity is equal to sand quantity.?
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
Why joints are provided?
Please tell me the quantity of cement, sand, flyash, foaming agent required for 1 cubic meter of cellular lightweight concrete blocks. also , is there any admixtures required for the CLC blocks production.
Which Types Of Bricks ?
what does the grad of cement shows (denotes)?
what is the proper procedure in conducting a california bearing ratio penetration test on soil on cbr machine?
What is the difference between undo & redo?
in the construction of residential building what type of tank are used?where?why & what is its purpose?
Explain what is 1/8 on the architect ruler denotes?
What is the difference between built area and super built up area?
how to calculate load for a bungalow and 1column carry how much load if the size of column ,9"*15" .....or total structure load......
what is meaning of inverted beam.is it way to provide double mat in slab one at bottom and another at topif we go for provision of inverted beam. shall we construct structure with out plinth beam for us we have to construct small bus shelter
we want build 10ft height ,tostore 4 litresof water.what is theground basement for steel andcement andsand.please send us basment calculation?
How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?
Why should pumping be not used in case of concreting work?
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?