for preparing 10cum of 1:4:8 cement concrete the
requirement of sand is
0.7cum
2.8cum
4.74cum
18.40cum
& how
Answer / engr.asad ali
we know that
Total wet volume of concrete = 10Cu.m
First we find dry volume
Dry volume = wet volume X 1.54
Dry volume = 10 X 1.54 = 15.4Cu.m
Determine sum of ratio = 1+4+8 = 13
And also we know that
Quantity of Sand = ration of sand X wet volume
-------------------------------
Sum of ratio
Quantity of sand = 4 X 15.4
-----------
13
Quantity of Sand = 4.738 Cu.m say 4.74Cu.m
| Is This Answer Correct ? | 71 Yes | 4 No |
what is parametre for M25 after 7 days strength
what do you know that m20,m25
how to calculate the number of cement bags required for 1m3 of work
iam constructing a new hall of size 21'*14'. we r constructing without columns...i.e only with basement..and constrcting wall thickness of 9" only...can I laid slab on these walls? is it safe?
Lime used for white washing is- (1) quick lime (2) Hydrated lime (3) caustic lime (4) lime milk
SHEAR FORCE AND BENDING MOMENT DIAGRAMS
What is the difference between EPC,DBOOT and BOOT.
03. a. The water cement ratio for achieving maximum strength of concrete is…… 1 b. Water/ cement is inversely proportional to-------------- 1 c. Increasing the slump decreases the strength: True / false 1
what is stress?
What is the Roll of Water Bonding under VDF road?
How to activate isometric axes in cad?
How manu days after the casting of a slab another slab can be casted above it? what is the total curing time of a slab if ponding is not done on it?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)