for preparing 10cum of 1:4:8 cement concrete the
requirement of sand is
0.7cum
2.8cum
4.74cum
18.40cum
& how
Answer / engr.asad ali
we know that
Total wet volume of concrete = 10Cu.m
First we find dry volume
Dry volume = wet volume X 1.54
Dry volume = 10 X 1.54 = 15.4Cu.m
Determine sum of ratio = 1+4+8 = 13
And also we know that
Quantity of Sand = ration of sand X wet volume
-------------------------------
Sum of ratio
Quantity of sand = 4 X 15.4
-----------
13
Quantity of Sand = 4.738 Cu.m say 4.74Cu.m
| Is This Answer Correct ? | 71 Yes | 4 No |
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
what is the development length?
How calculate the water for 1m3 concrete
What is the veriplus for ellips card length formula (major axis 3.4m,minar axis 2.6m spacing 0.2m
how can we calculate costing of a project per sqft/sqm
1 Answers Associate Consultant, AVT, L&T,
specific gravity of sand, coarse aggregate, cement.
How to estimate quantity of paint in 1M3
How to make a c++ program that converts any base to base 10?
which is higher specific gravity or bulkdensity
Weather we heat cement, will it changes its color? if yes why? if no why?
what is the safe bearing capacity of hard murum? can we consider it 50 ton?m2
how to calculate cement coefficient for 20mm thick vitrified tiles flooring with cm 1:4 with explaination
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)