how to calculate the number of cement bags required for 1m3
of work
Answers were Sorted based on User's Feedback
Answer / sumair jain
Grade Quantity(bags)
M5 2.83
M7.5 3.48
M10 4.52
M15 6.45
M20 8.22
M25 11.304
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / mujtaba
In 1 m3 concrete cement bags are 7.82 bags M25 grade concrete and w/c ratio .45
Is This Answer Correct ? | 0 Yes | 2 No |
Answer / pradosh pradhan
FOR M20 = 1:1.5:3
CEMENT = 1/5.5*1.57=.285 CUM.
AS PER CIVIL ENGG 1 CUM CONSUME 1440KG=28.8 BAGS
SO 0.285 CUM = .285*28.8= 8.2 BAGS
Is This Answer Correct ? | 3 Yes | 6 No |
Answer / m.r.prabhu
unit weight for cement varies from 1440 to 1650 kg/m^3..one bag of cement weighing 50 kg then it varry 28.8 to 33 bags of cement according to its unit weight...
Is This Answer Correct ? | 1 Yes | 8 No |
what is the procedure of plastering..?
Currently how much cost are coming in residential building per sqm with material & Labour rate in Delhi,NCR
Why we use sin wave only in ac not use any other form of wave?
what is floating slab foundation?
Which type of question ask for written test for civil diploma trainee
Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?
What is anchorage length
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
What is unit weight of 1st class bricks ?
qube strenth in 7nth days test
how to stop beam concrete between column
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day