Middle point of any slab is raised 10-12 mm during
shuttering work because––
Answers were Sorted based on User's Feedback
Answer / mughalsab
if i dont raised at mid ponit of slab so when we poured concrete then the slab is sag at mid point due to its own weight therefore we raised at mid point so when concrete is poured then the slab is going to its corect position.
Is This Answer Correct ? | 9 Yes | 1 No |
Answer / bharat gurav
because at middle point act point load & share force act at
L/4 so extra steel r provided...............but at mid-span
no provide extra steel due 2 sla raise 10-12mm
Is This Answer Correct ? | 1 Yes | 4 No |
In case of tunnels (Railway) what is the way of securing a wall beam?
How to design a beam without any typical(tuff) calculation. Answer Only by using site practical knowledge?
How can we improve the capacity of a existing foundation?
what is plum & mass concrete?
What is missing report and how to prepare
if dia of slab beam bar is38mm what its clear cover any method of provide clear cover
What is bmc stands for in bmc software?
what is the minimum cement content for rcc as per is code
How to preparation billing for high rise building? anyhow can give the tips
What is the deffrence multistory bulding &highrise bulding
What is the m25
6 Answers Itd Cementation India, L&T,
1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?