Middle point of any slab is raised 10-12 mm during
shuttering work because––
Answers were Sorted based on User's Feedback
Answer / mughalsab
if i dont raised at mid ponit of slab so when we poured concrete then the slab is sag at mid point due to its own weight therefore we raised at mid point so when concrete is poured then the slab is going to its corect position.
| Is This Answer Correct ? | 9 Yes | 1 No |
Answer / bharat gurav
because at middle point act point load & share force act at
L/4 so extra steel r provided...............but at mid-span
no provide extra steel due 2 sla raise 10-12mm
| Is This Answer Correct ? | 1 Yes | 4 No |
What is 1/8 on the architect ruler denotes?
five requirements of infill panels for walls?
What are the different softwares used for cad?
For raft 3000mm thickness with T25150 mesh reinf in top and bottom what diameter can be used for chair to support mesh reinforcement
What are the tests to be conducted on cement?
What is value of S.F at Point of contaflexure?
What is line killa
Define Workability ?
For a RCC section with congested reinforcement , what is the compaction factor
3 Answers Arihant, GMR, Gulf International Contracting, NBCC,
What is the meaning of RCC NP3 Pipes
in construction feild make the column rods are uneven ( e.g 1 column we have 6 nos of bars that 6 nos of bars are varrious level- 1 bar 10';2 bars 9';3 bars 8') what is resion to put different level if difference are required or not?
what is the ratio of m50 grade in concrete block
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)