Middle point of any slab is raised 10-12 mm during
shuttering work because––
Answer Posted / mughalsab
if i dont raised at mid ponit of slab so when we poured concrete then the slab is sag at mid point due to its own weight therefore we raised at mid point so when concrete is poured then the slab is going to its corect position.
| Is This Answer Correct ? | 9 Yes | 1 No |
Post New Answer View All Answers
PL.tell me about civil engineering questions with answer
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.
What are the steps involved in the concreting process?
what s the standrd size of pvc fittings ,like elbow, bend,tee etc ? please explain with figure ?
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?
how many kg of 20mm, 10mm, dust available in one ton stone boulder
What is the use of offset command?
Which is the latest version of solidsworks?
How to test cement,sand,20mmbluemetal,40mmbluemetal,bricks,concrete by visual and instrument
How do you calculate load bearing capacity of a waffle slab?
115mm thickness brick work how to required mortar
difference between trapezoidal and pedestal footing and how the load acts on that
How can i do RCC rate analysis?
What are the different theories of failure under static load?
What is the yield of 100 litres of water and 10 kg of cement in grout mix?