1. Insulation Resistance Measurement
a . For LT systems, use only 500V or 1000V Megger
b. For MV & HV systems, use 2500V or 5000V Megger
c. Remove Earth from Transformer neutral
2. Winding Resistance Measurement
R-N AND r-n
Y-N y-n
B-N b-n
3. Magnetic Current Test
Applied Voltage : RY YB BR
Measured Current : R Y B
4. Magnetic Balance Test
5. Vector Group Confirmation.
6 . Short Circuit Test and Differential Stability.
7 . REF Stability Test
8. Cooler Circuits.
9. Auxilliary Protection Circuits

Is This Answer Correct ?    2 Yes 0 No

In Transformer testing at Shop test we normally test for vector group, open ckt.,short ckt. but wha..

Answer / brahma

Also Double voltage double frequency, if customer ask impulse

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

I need HT sphere gap calibration table. Can any body help me.

0 Answers  


what is the setting of locked rotor in HT motor ? (answer expecting in percentage)

0 Answers  


How PSV sizing being done

0 Answers  


In diesel generator how AVR get voltage to excitation. And basic diagram DG EXCITATION CIRCUIT.

0 Answers   Hyatt,


What is the difference between vector surge relay (78) and Pole slip relay (98G)

0 Answers  






what is the tolerance for the magnetic balance test conducted on the distribution transformer?

0 Answers  


A 10 kva ,400v/200V , single phase transformer with 10% leakage impedance draws a steady short -circuit line current of

1 Answers  


What is maximum demand and contract demand?

5 Answers  


what is phase angle ? and also tells me why my phase-phase voltages are 390 rather then my single phase voltages are 221 and 223 respectivly?

2 Answers  


how to amps calculate from 1KVA?

11 Answers  


method to check earthing

5 Answers   ECC,


Why tripping not occur when the transmission breaks? Doesn't we provide earthfault protection for it?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)