In Transformer testing at Shop test we normally test for
vector group, open ckt.,short ckt. but what are the other
test performed for transformer once it reaches at site.For
e.g:if the transformer is dry having rating 1000KVA?
Answer Posted / guest
1. Insulation Resistance Measurement
a . For LT systems, use only 500V or 1000V Megger
b. For MV & HV systems, use 2500V or 5000V Megger
c. Remove Earth from Transformer neutral
2. Winding Resistance Measurement
R-N AND r-n
Y-N y-n
B-N b-n
3. Magnetic Current Test
Applied Voltage : RY YB BR
Measured Current : R Y B
4. Magnetic Balance Test
5. Vector Group Confirmation.
6 . Short Circuit Test and Differential Stability.
7 . REF Stability Test
8. Cooler Circuits.
9. Auxilliary Protection Circuits
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
what is the calculation method to design core and winding of a 200kva 3phase distribution transformer?
hey guys i scored 910 on GRE and 67 on TOEFL respectively.I have an aggregate of about 74%in my B tech.For which colleges should i apply for an MS program in electrical engineering.I am looking for colleges in NJ,SC,NC,GEORGIA, NY. Please reply with a good response.....
Explain difference between stand by earth fault and residual earth fault protection?
Classify driling machines.
sir, 3phase induction motor takes different pf and different KW in three phase while running,explain reason
If Neutral Grounding Resistor (GR) failed/shorted. Is it repairable.
What is lifting power for 1 wb/m2 and 1 A magnet?
WHY L-G FAULT IS MORE SEVERE IN TERMS OF RRRV?
why electron produce magnetic field when it is in motion?
my UPS suddenly goes off and all panel light also blow off.This happens even main electric supply is not interrupted.After some time it automatically starts functioning normally.Batteries are new.
Is there any abbrevation for STUB in Stub bus protection
What is Servo Ventilated Motor?
i want to put single phase load on scott connected transformer,eventhough how to balance the transformer.
what is the minimum pay scale for electrical engineer (building construction)in kuwait? plz revert back with yrs of experience & pay scale respectively.
how to find 5 kilo meter long under ground 33 kv cable fault location if IR VALUE shows 0.05 M ohm @5000 volt.and cable fault locator shows some time fault distance 3 kilo meter ,3.7 kilo meter and some time 1 kilo meter? now how to find the fault location that where is leakage. note--it is tested with 5000 kv megger and insulation resistance is 0.05 M ohm. and some time 0.03 M ohm comes.