Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

In Transformer testing at Shop test we normally test for
vector group, open ckt.,short ckt. but what are the other
test performed for transformer once it reaches at site.For
e.g:if the transformer is dry having rating 1000KVA?

Answer Posted / guest


1. Insulation Resistance Measurement
a . For LT systems, use only 500V or 1000V Megger
b. For MV & HV systems, use 2500V or 5000V Megger
c. Remove Earth from Transformer neutral
2. Winding Resistance Measurement
R-N AND r-n
Y-N y-n
B-N b-n
3. Magnetic Current Test
Applied Voltage : RY YB BR
Measured Current : R Y B
4. Magnetic Balance Test
5. Vector Group Confirmation.
6 . Short Circuit Test and Differential Stability.
7 . REF Stability Test
8. Cooler Circuits.
9. Auxilliary Protection Circuits

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

I want to know Electrical Circuit?

2163


what is package substation.how many types they have

2102


How we calculat the NGR of 3phase Generator, Our generation voltage 11KV

3308


distribution is maximum done by a)radial b)network c) parallel d)b & c

1937


What is Phase to Phase clearance for 800V System Operating Voltage as per IEC61439

1031


What is the drawback of class b amplifier?

1161


what causes contact chatter when there is no demand on the air conditioning unit?

2031


HOW TO WRITE A QUENTION ANSWER? I MEAN SHORT OR LENGHTHY ? OR FROM THE BOOK AS BOOK..... SOME TIME WE GIVE A ANS FROM THE BOOK AS LIKE BOOK ND WE GET MINIMUM 60% MARKS OR MORE THEN....... THEN HOW TO FILL THE Q-PAPER?

2045


Why the cores of large transformers build up of circular cross section?

2286


when qty of cable being purchased is not sufficient according to the standard,what should the inspector do to ensure its quality according to the standard?

2074


What is the general system requirement of alternator?

1841


WHAT IS DIFFERENCE BETWEEN MANUAL CONTROL AND MAGNETIC CONTROL AND STATE ITS ADVANTAGE /DISADVANTAGE

2080


defult setting in p220 micom motor proction relay for 11kv,640kw,f.l.a.-40a,1440rpm ht motor?

3697


What are the basic elements used for modeling mechanical rotational system?

1103


A cotter joint is generally used to transmit

1241