one MT of steel for using how much binding wire required?
Answer Posted / neel
8 kg / MT
Is This Answer Correct ? | 19 Yes | 3 No |
Post New Answer View All Answers
How to Calculate Materials Required for PCC 1:4:8 for 1Cum & Brickwork 1:4 for 1Cum & Plastering 1:4 (15mm Thick) for 100Sqm & RCC 1:4:8 & 2mt ( L1=1mt & L2=1mt ) length of 12mm Steel bended in 90degrees what is the formula to calculate Weight & Actual Length ?
how much is the maximum compressive strength of soil cement and soil-cement-microsilica .
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you
What distance in meters on the ground is the equivalent of one second of arc in longitude or latitude?
how clculate excavated or backfilling quantity by simpson's rule
What is the Roll of Water Bonding under VDF road?
How can i do RCC rate analysis?
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
in the earthquqke the profile of water on dam is parabolic or not
Explain the design for rcc multi-storied building?
How do you measure water flowing through 300mm diameter pipes?
significance of specific surface area of particles?
what is the mode of method of face bar measurement
What are the ingredients of pre-stressed concrete?