how to calculate the number of cement bags required for 1m3
of work

Answer Posted / pradosh pradhan

FOR M20 = 1:1.5:3
CEMENT = 1/5.5*1.57=.285 CUM.

AS PER CIVIL ENGG 1 CUM CONSUME 1440KG=28.8 BAGS
SO 0.285 CUM = .285*28.8= 8.2 BAGS

Is This Answer Correct ?    3 Yes 6 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the standard specification of MOR and Water Absorption of Homogenous Ceramic Floor Tiles?

1775


how do we design mix ratio?

1423


How foundation is designed, Column design and beam design

1858


how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.

2239


How to compute minimum number of columns required for a site from area of site?

1534






What is a bearing capacity of soil?

811


Explain the different types of building contracts?

660


How to find beam R/F cutting length

1228


what is the price of a cubic meter of concrete on international market?

639


What is hybrid foundation?

685


What is the meaning of soil reinforcement?

663


why we use 19x9x9and 20x10x10 but not other

1735


Which brick is best for construction ,either fly ash or AAC BLOCKS

582


Questions related to civil.engg in company

1573


TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING

2096