how to calculate the number of cement bags required for 1m3
of work
Answer Posted / pradosh pradhan
FOR M20 = 1:1.5:3
CEMENT = 1/5.5*1.57=.285 CUM.
AS PER CIVIL ENGG 1 CUM CONSUME 1440KG=28.8 BAGS
SO 0.285 CUM = .285*28.8= 8.2 BAGS
Is This Answer Correct ? | 3 Yes | 6 No |
Post New Answer View All Answers
What is the standard specification of MOR and Water Absorption of Homogenous Ceramic Floor Tiles?
how do we design mix ratio?
How foundation is designed, Column design and beam design
how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.
How to compute minimum number of columns required for a site from area of site?
What is a bearing capacity of soil?
Explain the different types of building contracts?
How to find beam R/F cutting length
what is the price of a cubic meter of concrete on international market?
What is hybrid foundation?
What is the meaning of soil reinforcement?
why we use 19x9x9and 20x10x10 but not other
Which brick is best for construction ,either fly ash or AAC BLOCKS
Questions related to civil.engg in company
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING