how many bags of cement required in neat cement finish per
square metre
Answers were Sorted based on User's Feedback
Answer / mahbub alam
Use 1bag cement=(16.5-18.5)sq.m Neat finishing
so 1sq.m contains (2.7-3)kg.....
| Is This Answer Correct ? | 59 Yes | 4 No |
Answer / sanchit guleria
1oo sq. ft = 9.3 sq.m contains 6 bags of cement.
so 1sq.m contains .65 bags = 32.5kg of cement
| Is This Answer Correct ? | 14 Yes | 28 No |
above answer is wrong. simply
for one Sqm of neat Cement Finish With 15 mm thick plaster -
0.145 Bags of Cement Required For Sqm.
Calculation = 0.145 * 290=42.05
Sand = 0.015*1260 = 18.9
total Material Cost = 60.95
Labour Cost is = 90 / SQm
So all together = 150.95 Say 150.
from ur calculation
for one Sqm = 32.5 kg of cement
that means = 32.5 X (290/50)= 188.5 / Sqm
is it Any boq Neat Finish gave above 300/
| Is This Answer Correct ? | 4 Yes | 19 No |
How musch steel i.e. angles, channels,and square pipes are required per square feet for a steel roof of residential two storied building?
1.why can't we used sea sand in construction? 2.can we change sea sand into normal sand? if yes how?
What is standard Sand? What is Regime condition? What do you mean by the core trench in Earthen Dasm? What is soundness test for cement? When negetive shear force takes place in a R.C.C member?
What will be the crank length in an staircase is same like an slab?
what is the voice of ratio ?
is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.
find the discharge of water through a horizental venturimeter having 400mm dia at the inlet main and 150mm dia at thorat.if the diffrential gauge between inlet and thorat shows a pressure head of 25cm mercury. assume coefficient discharge 0.98 and specfic gravity of mercury as 13.6.
What was asked in isro civil interview
1sqm tile laying how much cement required?
Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem
how much quantity of paint is required for 1 square meter wall for single and double coat..?
how to calcualate the amount of stone,cement,sand required for 1cum of 450mm thick ruble stond masonary with ratio1:5, please me an answer with dtailed step
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)