Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


In barbending schedule why is o.42*D is taken. Means why o.42 only???



In barbending schedule why is o.42*D is taken. Means why o.42 only???..

Answer / arghya das

that is 1.42d-d=0.42d
(1.42d comes from 1/sin45) 45 degree crank bar.

Is This Answer Correct ?    4 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

How many required steel of 1m3 slab casting?

3 Answers  


What kind of soil has what bearin for pile work? eg sand with high water table collapses faster, black cotton soil is ideal, sand leads to more wear and tear of the boring consumables, rock takes longer and require rock augers etc etc

1 Answers   HCC,


Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.

0 Answers  


How to find the no. of main bar in circular footing (Central shaft of CLF)

3 Answers   N J Devani Builders, Simplex,


what are the CAD software versions you have used?

12 Answers   ERA, IES,


If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?

0 Answers   Talib and Shamsi Constructions,


how do you stabilize a waterlogged area in road construction

0 Answers  


what is the formula to calculate costing of rubble soling and wbm in road works?

1 Answers  


how much quantity of cement bags are required to fill the one m3 of empty container.?

12 Answers   L&T, NBDL, SEW Infrastructure,


If drainage is main things then which respect the super Elevation may be provided?

4 Answers  


how can calculate cutting length of diamond ring

0 Answers  


what should be the minimum diameter of chairs in renforced concrete slab or raft roundation?

5 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)