Answer / harikirangowda
plastering should be competed from bottom to top except
skirting area bcz flooring have to complete before skirting ,,
| Is This Answer Correct ? | 4 Yes | 2 No |
Answer / sagar bothare
First tiles was immerse in to water till 1 hour
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / sachin
We firstly check FFL thiyyas of both flats or rooms and check right angle of room which we laid tiles, slab cleanses work, electrical pipe under the tiles mortar.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sjtbehera
ok first you can either fix wall tile or floor tiles it
does not matter. precaution is finishing on the edge.
| Is This Answer Correct ? | 0 Yes | 1 No |
Answer / mr.sagar .y. bothare
CEMENT MORTOR IS APPLIED ON THE WALL SURFACE. THEN TILE IS
SUBMERGE IN TO THE WATER UPTO 1 HOUR . THEN THIS TILE
SHOULD BE FIX TO THE WALL
THIS IS PROCEDURE TO FIX THE TILE.
| Is This Answer Correct ? | 0 Yes | 3 No |
How many Rod required for 58 feet by 24 feet roof slab which is supported by 5 * 3 = 15 Column. Six Stored building Roof Slab = ? Ton 15 Column = ? Ton Slab Beam = ? Ton
difference between limit state method and working stress in terms of load
what is the minimum depth of cover required for pipes?
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
if L*B*H = 20 then direct no of bricks =20 *500
WBM Road aggregates quantity calculation
IS code for grade of concrete for bamboo lintel????
what is the meaning or full form of 12T13 cables used in prestressed bridges
what is the permanent solution applied for restoration of leaning tower of pisa?
What is the graphical relationship between N - Value of soil and Dia. of pile when pile length is fixed, and n - Value and length of pile when its dia. is fixed.
how do you intend to overcome such challenges?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)