Answer / basirul islam
The standard size of masonary bricks is =19cm*9cm*9cm
=0.623ft*0.295ft*0.295ft
=0.0542cub feet
so no of bricks in 1cubfet =1/0.0542 nos
=18.45 nos
| Is This Answer Correct ? | 19 Yes | 18 No |
Answer / fazal haq khan
1350 Bricks in 100 cft
so Than
1350 / 100 =13.5
we know That
Now
we have Find
1Cft =13.5 Bricks
So The Ans Is
13.5 bricks In 1 Cft
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / amir shehzad
Check my blog for detail answer sheet.
http://bricks-calculations.blogspot.com/2011/07/proof-of-135-brick-in-1-cft.html
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / shehzad nazar
Guys you can follow this link to check how it works for bricks calculations. also an online sheet to get number of bricks for each size.
http://qs-learner.blogspot.com/2016/04/bricks-calculation.html
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / surya prakash upadhyay
1 cub feet volume have 15 bricks
| Is This Answer Correct ? | 1 Yes | 1 No |
Answer / robin
1 cubic feet = 14.769 bricks with hole, without mortar
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / johnpeterraj001@gmail.com
1 cubic feet is 11.62 bricks in practical constraction
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / ijaz
volume of brick= .75'x.25'x.375'
volume=.070cu ft
now in 100 cft = 100/0.070
=> 1428.57 nomber of bricks
now 10% mortar /////
deduction of mortorr= 10x1428.85/100 = 142.85
nomber of bricks
so net number of bricks = 1428.57-142.85= 1285.72
now for contengencies = 5%
so => 5x1285.72/100= 64.28
now the total number of bricks= 64.28+1285.72=1350.0061
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / dommeti kishore
One cubic metre contains 512 bricks .Hence proved
| Is This Answer Correct ? | 0 Yes | 0 No |
How to calculate woden area in sft and Cft
binding wire requirement in rcc structures
what is the difference between onw way slab & two way slab?
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
what is plum & mass concrete?
What is the correct position of lapping splice of reinforcement steel bars in a beam at top & bottom of the beam?? what is the reason for this location?..what are the factors affecting lapping location in beam?
lap length formula
what are the differences between Tie beam, Ground beam and strap beam. thanks
why provide water stopper in costruction joits
A bill was raised by contractor which read as follows 1.) Excavation in normal soil upto 1.5m - 250 cum 2.) Excavation in normal soil 1.5m to 3m - 240 cum 3.) Excavation in soft rock - 350 cum 4.) Excavation in hard rock - 250 cum 5.) Filling with available soil - 825 cum 6.) Filling with bought out soil - 1100 cum How can I verify the above quantities, especially for item no. 5 & 6? What checks are necessary before releasing the bill ?
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day
What is the unit standard weight,thicknessof C.I>Pipe of various Dia upto200 MM(as per IS1538)
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)