How to Calculate steel
Answers were Sorted based on User's Feedback
Steel can be calculated by kg or tonnes.
STEEL WEIGHT CAN BE calculated BY THE FORMULA OF
= D*D/162
D :- Daimeter of steel bar
| Is This Answer Correct ? | 125 Yes | 5 No |
Answer / prabhanshu gupta
Steel can be calculated by kegs or tonnes
Steel weight = Bar Length*D*D/162
D= Diameter of the bar
| Is This Answer Correct ? | 22 Yes | 7 No |
Answer / sachin
if wt of steel is to calcullated then
steel=(d*d)/162
if area of steel is to be calcullated then
Ast=((0.5fck*b*d)/fy)*((((4.6Mu*10^6)/fck*b*d*d)))
| Is This Answer Correct ? | 15 Yes | 5 No |
Answer / sankarji.ar
Example
Weight of 16 dia bar,per Kg/mtr
d:- 16
r:- 8
Area = πr2
=22/7*8*8
=201.14
=201.14*.00758
=1.524 Kg/mtr
By same way we can calculate different dia of bars...
------------------------------------------------------------
=(d*d)/162 its Thumb Rule.
| Is This Answer Correct ? | 8 Yes | 1 No |
Answer / muhammad qasim
When given question ft? then we use this formula
No of bars x total length x (suter)^2 / 24
then all answer divide to 2.204 it will give kg.s
example
room size 10 x 12
Step 1
total distance divided by .75 then + 1 (.75 is c/c distance)
it gives 14.333 say 15 No (same step as second dimension)
Step 2
(15 x 10 x (4)^2/24) then divide 2.204 = 45.37 kgs
where
4 mean 0.5 inch dia
| Is This Answer Correct ? | 6 Yes | 1 No |
Answer / muhammad tasawar riaz
Steel can be calculated by kegs or tonnes
Steel weight = Bar Length*D*D/24/2.204
D= Diameter of the bar
| Is This Answer Correct ? | 13 Yes | 9 No |
Answer / razeen
Steel Weight calculation for 1 meter
D*D/162.162
D = Diameter of the bar
Example: 25 mm bar
(25*25)/162.162
3.854 Kg per meter
| Is This Answer Correct ? | 1 Yes | 0 No |
9*9m 1:4:8 ratio using what quantity of 40mm aggregate, sand&cement please tell anwser
what is the material consumption of 1:2:4 by kilogram?
PERT Chart
Cement , sand , concrete ration in M30 Grade
How much cement ,steel bar, concrete ,required for 416 cum rcc slab
18. What is the thing that might make you happy at your work place?
In an aggregate blending plant, water is sprayed before blending is performed. If the fine content in aggregate is as high as 25 %, will not the fines form into lumps / balls and distribution will not be uniform ? Further, the fines will stick onto the interior of pug mill and its content will be low. The mixed material is stockpiled for weeks / months before use. Will it not be better that blending is done in dry condition, and water will be added only during compaction at site. Please forward your comments and suggestions.
what is design mix of M10, M20, M35, M40 grade of conconcrete?
1 Answers ILD, Lok Sewa Aayog, Raheja, Vishwa Infrastructures,
how to calculate the quantity of plaster.
What is the Roll of Water Bonding under VDF road?
what is difference between GTS bench mark and temporary bench mark
What is water/cement ratio? Importance in construction?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)