what is the difference between site engineer & site incharge
Answers were Sorted based on User's Feedback
Answer / sjtbehera
Site engineer is responsible for site execution.
but sit incharge is responsible for project execution
| Is This Answer Correct ? | 14 Yes | 5 No |
Answer / mayank jain
site engineer is responsible for a design factor and management of activities on the site .
site in-charge is responsible for a labor management and
material wastage.
| Is This Answer Correct ? | 10 Yes | 12 No |
Answer / prafulla
site engineer execute the work only
site engineer execute the work and all site material
machinery and manpower at timing
| Is This Answer Correct ? | 3 Yes | 6 No |
Answer / ameer
Site engineer responsible , he maintained more than 3 sites in particular area.
Site In Charge responsible, he maintained that particular one site, he managed the all works.
| Is This Answer Correct ? | 2 Yes | 8 No |
How to calculate the dia of reinforcement when required (as per drawing) dia of reinforcement steel not available at site?
3 Answers MNC, N J Devani Builders, Simplex,
Construction joint of beam & slab is provided at––
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
volume of one cement bag
4 Answers Grand Peaks, Omace, Swasudha Infra,
What is grouting? Why it is done?
please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)
Sand density
Define What is the origin of name Railway Sleepers?
where does the hinged action while designing the strture
Let suppose A building wall is 12 ft high and 30 ft long and labour cost is 100 rupee per feet so calculate the total cost of labour and also explain in detail...plz ans me immadiately i am hurry Thanx
What is the zero value in quantity surveying
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)