What is the procedure of Make to order configuration. Plz
answer me, Thanks in advance.
Answers were Sorted based on User's Feedback
Answer / navneet
make to order is a business process used in vc(variant configuration).
in this type of configuration we have configuration material type KMAT/ with item category as TAC/ item category group as erla or for configurable mat as 0002 or 0004
although there is a very lengthy setting with wide integration
with mm/pp/co/sd modules the basic process is as follows
once the order is created the requirement is transfered to
mm/pp there production order is created and material is produce in production facility. once material is produced it is received as storage facility with GR. then the material is picked for delivery pgi and billing.
THIS ANS IS BASED ON PERSONAL KNOWLEDGE. PLEASE REFER OTHER RELIABLE SOURCES ALSO
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / giddalur
FOR MTO ITEM CATEGORY SHOULD BE MAINTAIN IN MATERIAL MASTER
AS 0001 (CONFIGURAL) SAME AS ITEM CATEGORY GRUP,
& RAISE THE ORDER AND OBSERVE INE ITEM ITEM CATEGORY AS TAK
SC LINE CP ND requiremnt type as ke ,,THROUGH THE SALES ORDER
STOCK WIL BE POSTED IN MB1C
Is This Answer Correct ? | 0 Yes | 1 No |
Answer / shriya
Make to order comes for Porject system .
The steps to be fallowed are :
1. IN mm02 the general item category group in basic data 1
& item category group in sales org 2 should be make to order
The material type will be kmat or configurable materila
The order type will be PV and item category will be PVN
You need to create for item proosal witt- code va51
Then create master contract usingva41 and with create
operating contract using VA 41 w.r.t MASTER CONTRACT
Create sales order with respect to master contract using VA01
Create delivery with respect to sales order through VL01N
and do picking and packing and go for bill of landing at
header level and do PGI - vl02n
Do collective billing based on order through VF04 and take
the base as sales document .
Go to FB01 and do the account posting the document type
should be RV
Go to vf44 and do revenue recognisation based on future
posting period
The billing type will be periodic one
You can check all your reveue report in VF 45
Here afterFICO Come into picture to do FB01N and FB05N
Is This Answer Correct ? | 1 Yes | 5 No |
How do you control entry possibility of condition values at order through condition type settings?
What is CR (change request)in support project? can i have answer with real time example please.
Can anyone tell me please how can I go and introduce the discount condition type in the pricing procedure and how it’s going to impact with tax all the pricing getting to calculate in the order? For example, how specially I have a customer who I set out as an international customer and as a domestic customer what are the differences between that… is there tax is different, is there any fright different, is there any pricing different????
that is use with cash discount and with out cash discount in fields in fd32.
Can anyone share some tickets specially on pricing?
Can we create a sales order without plant? Is plant is one of the parameter to create a sales order?
Explain about smart forms?
How system picks up pricing while doing billing?
How to close the backorders?
Does sap transportation management require the use of sap event management? : transportation management
What copy control is and when copy control transition can be done? In what manner copy control transition can be done?
Which partner function is relevant when it comes to tax calculation in the sales order?