how much quantity are required like cement,sand,aggregate
for (46*29*0.41)feet slab? how much this quantity can be
calculated?
Answer Posted / jaydeep
total area 546.94 cubicfeet = 15.60 cubic meter
now for aggregate = 15.60 x 0.9 = 14.04 cubicmeter
for cement = 15.60 x 6.25 = 97.5 bags
the ratio of cement, sand and aggregate is 1:2:4 needed
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
In earth work 1300 cum soil how to calculate how many liters require in water
Why steel rods are produced only in even dimensions?
How much the quantity of Dry material of Crush for 1:2:4 Concrete, using pan 3/8'' down....
How to Calculate Materials Required for PCC 1:4:8 for 1Cum & Brickwork 1:4 for 1Cum & Plastering 1:4 (15mm Thick) for 100Sqm & RCC 1:4:8 & 2mt ( L1=1mt & L2=1mt ) length of 12mm Steel bended in 90degrees what is the formula to calculate Weight & Actual Length ?
Why concrete barriers have curved surface profiles?
Which purpose we use deck anchor in bridges?
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
What is the compressive strength of fly ash bricks?
how to calculate weight of 1.8 cum of aggregate
The definition of national highway
how find the cut length of tringular ring and any formula find out the quantity of circular brick work
2. What are the advantages of your present job, things you like about it?
Explain what is 1/8 on the architect ruler denotes?
A doubly reinforced concrete beam is 25 cm wide and 50cm deep to the centre of tension reinforcement. The centre of compression is steel is 5cm from the compression edge. The areas of the compression and the tension steel are 10.16cm2 and 12.56 cm2 if m=18 and the bending moment at the section is 7,000,000 N-cm. Calculate the stress in concrete and steel.
plz drive the formula d2/162.162 for the calculation of weight of steel bars????