how much quantity are required like cement,sand,aggregate
for (46*29*0.41)feet slab? how much this quantity can be
calculated?
Answer Posted / jaydeep
total area 546.94 cubicfeet = 15.60 cubic meter
now for aggregate = 15.60 x 0.9 = 14.04 cubicmeter
for cement = 15.60 x 6.25 = 97.5 bags
the ratio of cement, sand and aggregate is 1:2:4 needed
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
What does civil engineering mean?
punj loyed and sapurjl palanjl
What is an object snap mode?
what is the relation between pitch of steel and depth of slab?
Explain major differences between routing maintenance and major maintenance.
What is meant by Crystal Concrete?
Can rice husk ash be used instead of coal fly ash for manufacture of clc/ foam concrete
for pretensioning which will yield first and same for post tensioning?
What are the different methods for drawing an arc?
Are cruise ships built for the transatlantic run?
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
crank types
What is the primary difference between adsorption and absorption?
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
How to do rate analysis for concrete work including shuttering work?