Answer / amit sharma
P2P means procure to pay.There is no standard it all
depends from organiation to organisation and business to
business.Generally stated the following would be the teps --
>
1. Purchase Requisition Creation (ME51n)
2. Approval of PR (ME54n)
3. PO creation and approval (ME21n and ME28/Me29n)
4. Goods Receipt (MIGO)
5. Invoice booking (MIRO)
6. Payment to Vendor (F-53)
The above the most common.In adition you can have Forecast
aswell.
Is This Answer Correct ? | 23 Yes | 0 No |
Answer / sowmya c
P2P is Procure to Pay and below are the T-codes we use in day today transactions.
1. Purchase Requisition Creation (ME51n)
2. Approval of PR (ME54n)
3. PO creation and approval (ME21n and ME28/Me29n)
4. Goods Receipt (MIGO)
5. Invoice booking (MIRO)
6. Payment to Vendor (F-53)
7. Display Material Document (MB03) - By using GRN number we can get PO details
8. Display Purchase Requisition (ME53N)- We get PR/PO details by using PR number.
ZFIR_PROVISION_REPORT (ZGL57) - We get PR/PO details by using PO number.
9. ZFIR_PROVISION_REPORT (ZGL57) - For Monthly Provisining
Is This Answer Correct ? | 5 Yes | 0 No |
Answer / mallikarjuna
P2P means Procure to Pay in general we call it as FI MM
integration.
Mainly FI/MM integration will happen in OBYC T code.
FI/MM integration is nothing but from Purchase requisition
to vendor payment.
ME21N: P O Creation
MIGO: Goods received against PO
MIRO: Invoice received aganinst the PO
F-53/F110: vendor Payment
Is This Answer Correct ? | 1 Yes | 2 No |
residual value key?
Why you use Asset Class ?
What is internal number range? What advantages & risk?
how to issue a single cheque payment for multiple open items for a single vendor in automatic payment program (f110). becoz normally we issue a single cheque for each open item, but if we want to issue a single for a number of open items then how to customise it?
What is document type, and what does it control? Examples.
Hi All. IN AR once the first dunning is sent to the client, after that how the system will know the next dunning need to be sent?
What is the Difference between SAP R/3 4.7 and 6.0.
what is mean by enterprise structure
How to Configure Parking document system in SAP.
what is the difference between the hold documents and park documents
I have blocked the Vendor Invoices in SAP at the time of preparing them in F-43 but when I have tried to Unblock them in FBL1N then system is just showing them they are blocked and not giving me the option to unbleck them. please help me out?
why we are require internal orders when we are using co+st centres.