what will do when 7days concrete has failed and structure has
constructed?

Answers were Sorted based on User's Feedback



what will do when 7days concrete has failed and structure has constructed?..

Answer / modipraveen

Hi,
Generally we will wait for 28th day test, If structure is
failure, then will intimate to Structural Consultant to
strengthen the structure.

Is This Answer Correct ?    19 Yes 1 No

what will do when 7days concrete has failed and structure has constructed?..

Answer / vimal prajapati

If 7 days result not getting,wait for 28 days.if 28 days
result not achived that perticular Quantity part breakdawn.

in any doubt with cube testing result we can also doing
core cutter test or rebound hammer test for at the 07 days
& 28 days sharp time period

Is This Answer Correct ?    4 Yes 1 No

what will do when 7days concrete has failed and structure has constructed?..

Answer / suresh bariya

Generally we will wait for 28th day test,if 28 days test
result get failed then immidiate inform your structural
consultant,consultant will suggest the rebound hammer test
which is not a perfect solution, then do the core cutting
test it will give you the actual result of that strucutural
concrete, from this result you will know the actual
strength ,it will decide the jacketing will serve the
purpose or brecking is the final solution.

Is This Answer Correct ?    2 Yes 0 No

what will do when 7days concrete has failed and structure has constructed?..

Answer / amilineni s babu

we have to wait for 28 days strength if it is also less we
have to go for core cutting or rebound hammer tests for that
particular structure part.

Is This Answer Correct ?    1 Yes 0 No

what will do when 7days concrete has failed and structure has constructed?..

Answer / karnam seenu

,When a cube test conducted for a structural member fails, it is advisable to go immediately for a core cutting test and send the sample slab core to test the compressive strength. You need not wait for 14 days or 28 days.

Is This Answer Correct ?    0 Yes 0 No

what will do when 7days concrete has failed and structure has constructed?..

Answer / suhana soni

i want to know.

Is This Answer Correct ?    0 Yes 5 No

Post New Answer

More Civil Engineering Interview Questions

pile load testing procedure

0 Answers  


Is there any alternate for plastering

1 Answers  


what is meant by geosyntahtic system

1 Answers   Bhel,


7. Do you apply the skills and knowledge learnt at school in your work?

1 Answers  


productivity of steel fitter per day

2 Answers   Shapoorji Pallonji,






What is c.g.i sheet which used for roof??

0 Answers  


why we used shahabad stone (ladi) in box type water proofing.what is the main roll of shahabad stone?

2 Answers  


What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.

0 Answers  


how to calculate no of rings & weight of column including rings?

2 Answers   HCC, Shivam Constructions,


Civil engineering related

0 Answers   HSS, Jaypee,


What is the difference between opc cement to ferro cement

1 Answers  


9*8m slab 1:2:4 ratio use for M20 mix how much cent is require it will become in cum but i want bags.

9 Answers   L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)